Skip to content
Gridcensus

EC Near Engineered Carbons Echo Cogeneration

Greenfield

Orange County, Texas · MISO

DC Readiness
49.5
Fair / 100

At a glance

EC Near Engineered Carbons Echo Cogeneration is a greenfield datacenter candidate site in Orange County, Texas, scoring 49.5/100 DC Readiness — 76th of 92 scored sites in the county. It sits in the MISO grid region, where interconnection has averaged 3.5 years from request to operation.

Power & interconnection

Nearest grid bottleneckMDOPHR99_A · 147 km (ERCOT)
LMP zoneERCOT_CENTRAL
Wholesale LMP$18.75/MWh
Utility commercial rate0.10¢/kWh

Speed to power

Interconnection outlookModerate
≈ 3.5 yrs typical interconnection wait

Middle-of-the-pack interconnection conditions for this grid.

ISO / RTO regionMISO
Queue depth24
Avg queue wait3.5 yrs
Recent queue wait3.5 yrs
Completion rate29%
Withdrawal rate71%

Connectivity

Nearest IXPEquinix HO1 - Houston
IXP distance102.5 mi
Fiber providers3
Fiber coverage30.8%
Nearest cloud providerGCP
Nearest cloud regionus-south1
Cloud region distance258.6 mi

Site characteristics

Site typeGreenfield
Land contactOrange County Assessor
Land owner typeprivate
Buildability15.0/100
Land cover (NLCD)Woody Wetlands
Former usenear retired gas plant (5km)

Risk & environment

Environmental constraintModerate (40/100)
Flood zoneZone AE (SFHA)
Water stress (WRI)2.80
Wetlands (NWI)Present
Critical habitatClear
Superfund nearbyClear
Hazard sub-score20/100
Construction cost index103.6 (avg 100)

Location context

Nearest datacenterDatacenter 01457383500
DC distance98.4 mi
Nearest rail0.4 mi
Nearest gas pipeline0.5 mi
Nearest fiber route104.2 mi
County hazard (FEMA NRI)Very High (55)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity9.60¢/kWh
Industrial electricity5.87¢/kWh
Cooling degree days2,600
Heating degree days1,800
Land price / acre$3,994

Regulatory climate

Favorablestate posture · as of 2026-08

No statewide moratorium, but since Aug 3, 2026 ERCOT has paused approvals to energize new datacenter and crypto loads ≥75 MW pending an audit due Dec 10, 2026. SB 6 adds large-load obligations above 75 MW.

DC tax incentiveYes
Large-load threshold≥ 75 MW

SB 6: loads ≥75 MW accept ERCOT emergency curtailment + contribute to interconnection cost.

Incentive detail: Chapter 313/Chapter 403 property tax abatements; Texas Enterprise Fund; no state income tax.

Site location

◆ Loading map…
≥ 7560–7540–60≤ 40
This site + 8 nearby

Get alerts

Track EC Near Engineered Carbons Echo Cogeneration

Get an email when its DC-readiness score, available capacity, or interconnection-queue status changes.

No spam. Just the alerts you asked for.

How does EC Near Engineered Carbons Echo Cogeneration compare with other sites in Orange County?

EC Near Engineered Carbons Echo Cogeneration ranks 76th of 92 scored candidate sites in Orange County. Its 49.5/100 is roughly in line with the county average of 51.7. It is about 12% below the Texas average of 56.4 and roughly in line with the national average of 53.2.

Against the Texas average, its strongest sub-score is water (61 vs 46) and its weakest is natural hazard (20 vs 44). Power and speed to power each carry 20% of the composite score, fiber 12%, water 7% and hazard 6%.

How close is EC Near Engineered Carbons Echo Cogeneration to power, fiber and other datacenters?

The nearest located transmission bottleneck is MDOPHR99_A (ERCOT), 91 miles away. For connectivity, the nearest internet exchange facility is Equinix HO1 - Houston at 102.5 miles. 3 fiber providers report service at the location in FCC broadband data. The closest operating datacenter on record is Datacenter 01457383500, 98.4 miles away.

What are the flood, water and hazard risks at EC Near Engineered Carbons Echo Cogeneration?

The site is in FEMA flood zone AE, a Special Flood Hazard Area — land with at least a 1% annual chance of flooding. WRI rates baseline water stress at 2.80 on a 0–5 scale. Mapped wetlands (National Wetlands Inventory) are present on the parcel. At the county level, FEMA's National Risk Index rates Orange County "Very High".

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
30
Speed to power20%
59
Fiber connectivity12%
56
Energy cost10%
93
Water risk7%
61
Natural hazard6%
20
Buildability7%
15
Labor market4%
50
DC cluster4%
20
Land / acreage3%
51
Construction cost3%
64
Gas pipeline2%
99
Tax incentive1%
100
Climate / cooling1%
0

Nearby comparable sites

Other scored datacenter candidate sites in Orange County, ranked by DC Readiness.

Sites near EC Near Engineered Carbons Echo Cogeneration
SiteTypeVoltageCapacityQueue waitScore
HARTBURGSubstation-Adjacent500 kV1,000 MW3.5 yrs60.7
UNKNOWN308840Substation-Adjacent345 kV600 MW3.5 yrs58.2
UNKNOWN304498Substation-Adjacent230 kV300 MW3.5 yrs57.2
UNKNOWN301088Substation-Adjacent230 kV300 MW3.5 yrs56.3
GULFWAYSubstation-Adjacent230 kV300 MW3.5 yrs56.3
UNKNOWN304113Substation-Adjacent230 kV300 MW3.5 yrs56.3
UNKNOWN300914Substation-Adjacent230 kV300 MW3.5 yrs56.3
VFW PARKSubstation-Adjacent230 kV300 MW3.5 yrs56.3

EC Near Engineered Carbons Echo Cogeneration: common questions

What is the DC Readiness score of EC Near Engineered Carbons Echo Cogeneration?

EC Near Engineered Carbons Echo Cogeneration scores 49.5/100 on the GridCensus DC Readiness scale, rated fair. It ranks 76th of 92 scored sites in Orange County. The Orange County average is 51.7 and the Texas average is 56.4.

What grid region is EC Near Engineered Carbons Echo Cogeneration in?

EC Near Engineered Carbons Echo Cogeneration is in the MISO region. Projects interconnecting there have averaged a 3.5-year wait from queue request to operation.

Is EC Near Engineered Carbons Echo Cogeneration in a flood zone?

The site is in FEMA flood zone AE, a Special Flood Hazard Area — land with at least a 1% annual chance of flooding.

Who owns EC Near Engineered Carbons Echo Cogeneration?

Parcel records list the owner as ENTERGY LOUISIANA LLC (private land).

How far is EC Near Engineered Carbons Echo Cogeneration from an internet exchange?

The nearest internet exchange facility is Equinix HO1 - Houston, about 102.5 miles away; 3 fiber providers report service at the location.

Related pages

About this data

Source: GridCensus composite of HIFLD transmission and substation data, EIA, FEMA National Risk Index, FCC broadband data, PeeringDB and ISO interconnection queues, as published October 10, 2026 — GridCensus refreshes it monthly. See the methodology for how records are matched, cleaned and scored.

Cite as: GridCensus, “EC Near Engineered Carbons Echo Cogeneration, Orange County, TX”, https://gridcensus.com/datacenter-sites/texas/orange-county/ec-near-engineered-carbons-echo-cogeneration-947808f6 (data as of October 10, 2026).

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

Every site and score for EC Near Engineered Carbons Echo Cogeneration, Orange County is free to browse. Pro adds Watchtower on 25 sites, alerts when new candidate sites, datacenters or interconnection-queue requests appear in your markets, score and capacity history, and CSV export. Enterprise adds team seats, weekly data files for all 147,272 sites, the REST API and an MCP server for AI tools.