DC Readiness
55.2
Good / 100

GROVER is a substation-adjacent datacenter candidate site in Sullivan County, Pennsylvania, interconnecting through PJM. It screens at 55.2/100 DC Readiness with a catalogued 300 MW of candidate capacity and a 3.8 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationGROVER
Substation distance0.0 mi
Substation voltage230 kV
Available capacity300 MW

Speed to power

ISO / RTO regionPJM
Queue depth31
Avg queue wait3.8 yrs

Connectivity

Nearest IXP70 Henry St
IXP distance58.7 mi
Fiber providers3
Fiber coverage29.9%

Site characteristics

Risk & environment

Water stress (WRI)Low
Wetlands (NWI)
Critical habitat
Superfund nearby
Hazard sub-score72/100

Location context

Nearest datacenterNautilus Cryptomine
DC distance51.4 mi
County hazard (FEMA NRI)Relatively Moderate (28)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity11.75¢/kWh
Industrial electricity7.95¢/kWh
Cooling degree days800
Heating degree days5,600
Land price / acre$4,619

Incentive detail: Keystone Opportunity Zone/KOEZ sales and property tax exemptions in designated areas.

Site location

◆ Loading map…
≥ 7560–7540–60≤ 40
This site + 7 nearby

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
78
Speed to power15%
32
Fiber connectivity12%
19
Energy cost10%
50
Water risk8%
90
Natural hazard8%
72
Buildability7%
60
Labor market4%
50
DC cluster4%
40
Land / acreage3%
42
Construction cost3%
50
Gas pipeline2%
10
Tax incentive2%
100
Climate / cooling2%
85

Nearby comparable sites

Other scored datacenter candidate sites in Sullivan County, ranked by DC Readiness.

Sites near GROVER
SiteTypeVoltageCapacityQueue waitScore
EC Coal Sullivan CountyGreenfield3.0 yrs57.5
EC Coal Sullivan CountyGreenfield3.0 yrs56.3
EC FFE Sullivan CountyGreenfield3.0 yrs56.0
EC Coal Sullivan CountyGreenfield3.0 yrs55.4
Mine SiteFormer Mine3.8 yrs49.1
Mine SiteFormer Mine3.8 yrs49.0
Mine SiteFormer Mine3.8 yrs48.9

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen