Skip to content
Gridcensus

Myer Solar

Brownfield

Ulster County, New York · NYISO

DC Readiness
58.0
Good / 100

Myer Solar is a brownfield datacenter candidate site in Ulster County, New York, interconnecting through NYISO. It screens at 58.0/100 DC Readiness with a catalogued 3 MW of candidate capacity and a 4.9 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationSAUGERTIES
Substation distance1.3 mi
Substation voltage69 kV
Available capacity3 MW
LMP zoneNYISO_ZONE_F
Wholesale LMP$39.50/MWh
Utility commercial rate0.11¢/kWh

Speed to power

ISO / RTO regionNYISO
Queue depth298
Avg queue wait4.9 yrs

Connectivity

Nearest IXPCyrusOne Wappingers Falls
IXP distance33.1 mi
Fiber providers12
Fiber coverage32.2%
Nearest cloud providerAWS
Nearest cloud regionus-east-1
Cloud region distance279.9 mi

Site characteristics

Site typeBrownfield
Land owner typeprivate
Buildability75.0/100
Former usemanufacturing
Existing capacity3 MW
Cleanup statuscleanup_complete

Risk & environment

Flood zoneZone X
Water stress (WRI)0.50
Wetlands (NWI)Clear
Critical habitatClear
Superfund nearbyPresent
Superfund siteUNIFORMS USA INC
Hazard sub-score55/100
Construction cost index89.8 (avg 100)

Location context

Nearest datacenterCyrusOne Wappingers Falls
DC distance33.1 mi
Nearest rail1.1 mi
Nearest gas pipeline3.7 mi
County hazard (FEMA NRI)Relatively High (35)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity11.47¢/kWh
Industrial electricity8.84¢/kWh
Cooling degree days700
Heating degree days6,100
Land price / acre$8,701

Incentive detail: Excelsior Jobs Program tax credits; IDA property tax abatements (PILOT); Empire State Digital Gaming.

Site location

◆ Loading map…
≥ 7560–7540–60≤ 40
This site + 8 nearby

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
32
Speed to power15%
40
Fiber connectivity12%
59
Energy cost10%
85
Water risk8%
90
Natural hazard8%
55
Buildability7%
75
Labor market4%
50
DC cluster4%
40
Land / acreage3%
57
Construction cost3%
75
Gas pipeline2%
88
Tax incentive2%
100
Climate / cooling2%
90

Nearby comparable sites

Other scored datacenter candidate sites in Ulster County, ranked by DC Readiness.

Sites near Myer Solar
SiteTypeVoltageCapacityQueue waitScore
HURLEY AVENUESubstation-Adjacent345 kV600 MW4.9 yrs60.0
Mine SiteFormer Mine4.9 yrs54.1
EAST KINGSTONSubstation-Adjacent115 kV100 MW4.9 yrs53.9
LINCOLN PARKSubstation-Adjacent115 kV100 MW4.9 yrs53.6
GALEVILLESubstation-Adjacent69 kV50 MW4.9 yrs53.4
TAP135701Substation-Adjacent69 kV50 MW4.9 yrs53.2
STURGEON POOLSubstation-Adjacent69 kV50 MW4.9 yrs53.0
HIGH FALLSSubstation-Adjacent69 kV50 MW4.9 yrs52.7

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for Myer Solar, Ulster County. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.