Bostwick (P-S)

Federal Excess

Nuckolls County, Nebraska · SPP

DC Readiness
50.0
Fair / 100

Bostwick (P-S) is a federal excess datacenter candidate site in Nuckolls County, Nebraska, interconnecting through SPP. It screens at 50.0/100 DC Readiness and a 3.3 yrs average interconnection-queue wait.

Power & interconnection

UtilitySOUTH CENTRAL PUBLIC PWR DISTnot availablefavorable to large load · state default

Speed to power

Interconnection outlookModerate
≈ 3.3 yrs typical interconnection wait

Middle-of-the-pack interconnection conditions for this grid.

ISO / RTO regionSPP
Queue depth27
Avg queue wait3.3 yrs

Connectivity

Nearest IXPBeloit-NOC
IXP distance39.1 mi
Fiber providers5
Fiber coverage67.3%

Site characteristics

Acreage35 ac
Buildable load (est.)~14–35 MWland-based
Former useReclamation and Irrigation

Risk & environment

Environmental constraintNone (0/100)
Water stress (WRI)Medium-High
Wetlands (NWI)—
Critical habitat—
Superfund nearby—
Hazard sub-score72/100

Location context

Nearest datacenterBeloit-NOC
DC distance39.1 mi
County hazard (FEMA NRI)Relatively Moderate (28)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity5.94¢/kWh
Industrial electricity10.59¢/kWh
Cooling degree days1,000
Heating degree days6,200
Land price / acre$5,127

Regulatory climate

Favorablestate posture · as of 2026-08

Public-power incentives; DC-friendly.

DC tax incentiveYes

Incentive detail: ImagiNE Nebraska Act: sales tax exemption on DC equipment; investment tax credits.

Site location

◆ Loading map…
≥ 7560–7540–60≤ 40
This site + 8 nearby

Get alerts

Track Bostwick (P-S)

Get an email when its DC-readiness score, available capacity, or interconnection-queue status changes.

No spam. Just the alerts you asked for.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
30
Speed to power20%
52
Fiber connectivity12%
68
Energy cost10%
50
Water risk7%
60
Natural hazard6%
72
Buildability7%
50
Labor market4%
50
DC cluster4%
40
Land / acreage3%
45
Construction cost3%
50
Gas pipeline2%
10
Tax incentive1%
100
Climate / cooling1%
75

Nearby comparable sites

Other scored datacenter candidate sites in Nuckolls County, ranked by DC Readiness.

Sites near Bostwick (P-S)
SiteTypeVoltageCapacityQueue waitScore
UNKNOWN132425Substation-Adjacent115 kV100 MW3.3 yrs56.2
TAP168328Substation-Adjacent69 kV50 MW3.3 yrs54.2
UNKNOWN168330Substation-Adjacent69 kV50 MW3.3 yrs53.5
UNKNOWN168329Substation-Adjacent69 kV50 MW3.3 yrs53.4
UNKNOWN157317Substation-Adjacent69 kV50 MW3.3 yrs53.2
Southward Elementary SchoolIndustrial——3.3 yrs50.3
Northward Elementary SchoolIndustrial——3.3 yrs50.3
Bostwick (P-S)Federal Excess——3.3 yrs50.0

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for Bostwick (P-S), Nuckolls County. Pro and Enterprise plans unlock the full 147,272-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.