Skip to content
Gridcensus

UNKNOWN131652

Substation-Adjacent

Douglas County, Nebraska · SPP

DC Readiness
60.4
Good / 100

UNKNOWN131652 is a substation-adjacent datacenter candidate site in Douglas County, Nebraska, interconnecting through SPP. It screens at 60.4/100 DC Readiness with a catalogued 50 MW of candidate capacity and a 4.3 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationUNKNOWN131652
Nearest grid bottleneckNEBS56S40S55 · 71 km (SPP)
Substation distance0.0 mi
Substation voltage69 kV
Available capacity50 MW
UtilityOMAHA PUBLIC POWER DISTRICTpolitical subdivisionfavorable to large load · terms ≥ 50 MW

Speed to power

Interconnection outlookModerate
≈ 4.9 yrs typical interconnection wait

Middle-of-the-pack interconnection conditions for this grid.

ISO / RTO regionSPP
Queue depth25
Avg queue wait4.3 yrs
Recent queue wait4.9 yrs
Completion rate16%
Withdrawal rate84%

Connectivity

Nearest IXPScott Data Center Omaha
IXP distance2.8 mi
Fiber providers17
Fiber coverage86.3%

Site characteristics

Risk & environment

Environmental constraintNone (0/100)
Water stress (WRI)Medium-High
Wetlands (NWI)—
Critical habitat—
Superfund nearby—
Hazard sub-score72/100

Location context

Nearest datacenterScott Data Center Omaha
DC distance2.8 mi
County hazard (FEMA NRI)Relatively Moderate (28)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity8.20¢/kWh
Industrial electricity5.80¢/kWh
Cooling degree days1,000
Heating degree days6,200
Land price / acre$9,113

Regulatory climate

Favorablestate posture · as of 2026-08

Public-power incentives; DC-friendly.

DC tax incentiveYes

Incentive detail: ImagiNE Nebraska Act: sales tax exemption on DC equipment; investment tax credits.

Site location

◆ Loading map…
≥ 7560–7540–60≤ 40
This site + 8 nearby

Get alerts

Track UNKNOWN131652

Get an email when its DC-readiness score, available capacity, or interconnection-queue status changes.

No spam. Just the alerts you asked for.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
46
Speed to power20%
54
Fiber connectivity12%
97
Energy cost10%
50
Water risk7%
60
Natural hazard6%
72
Buildability7%
60
Labor market4%
50
DC cluster4%
100
Land / acreage3%
50
Construction cost3%
50
Gas pipeline2%
10
Tax incentive1%
100
Climate / cooling1%
75

Nearby comparable sites

Other scored datacenter candidate sites in Douglas County, ranked by DC Readiness.

Sites near UNKNOWN131652
SiteTypeVoltageCapacityQueue waitScore
OPPD BLONDO STREETSubstation-Adjacent345 kV600 MW4.3 yrs68.2
OZ DouglasGreenfield——4.3 yrs66.8
OZ DouglasGreenfield——4.3 yrs66.2
EC Coal Douglas CountyGreenfield——4.3 yrs65.5
EC Coal Douglas CountyGreenfield——4.3 yrs65.3
EC Coal Douglas CountyGreenfield——4.3 yrs64.1
OZ DouglasGreenfield——4.3 yrs63.5
UNKNOWN132689Substation-Adjacent161 kV100 MW4.3 yrs63.4

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

Every site and score for UNKNOWN131652, Douglas County is free to browse. Pro adds Watchtower on 25 sites, alerts when new candidate sites, datacenters or interconnection-queue requests appear in your markets, score and capacity history, and CSV export. Enterprise adds team seats, weekly data files for all 147,272 sites, the REST API and an MCP server for AI tools.