Skip to content
Gridcensus

Chadron Substation

Federal Excess

Dawes County, Nebraska · SPP

DC Readiness
48.5
Fair / 100

Chadron Substation is a federal excess datacenter candidate site in Dawes County, Nebraska, interconnecting through SPP. It screens at 48.5/100 DC Readiness and a 3.3 yrs average interconnection-queue wait.

Power & interconnection

UtilityNEBRASKA PUBLIC POWER DISTRICTpolitical subdivisionfavorable to large load · terms ≥ 50 MW

Speed to power

Interconnection outlookModerate
≈ 3.3 yrs typical interconnection wait

Middle-of-the-pack interconnection conditions for this grid.

ISO / RTO regionSPP
Queue depth27
Avg queue wait3.3 yrs

Connectivity

Nearest IXPGolden West Rapid City Skyline Facility
IXP distance87.2 mi
Fiber providers5
Fiber coverage52.9%
Max download57 Mbps

Site characteristics

Acreage10 ac
Buildable load (est.)~4–10 MWland-based
Land contactDawes County County Assessor
Former usePower Development and Distribution

Risk & environment

Environmental constraintNone (0/100)
Water stress (WRI)Medium-High
Wetlands (NWI)—
Critical habitat—
Superfund nearby—
Hazard sub-score72/100

Location context

Nearest datacenterGolden West Rapid City Skyline Facility
DC distance87.2 mi
County hazard (FEMA NRI)Relatively Moderate (28)
DC tax incentiveYes (sales_tax_exemption)
Cooling degree days1,000
Heating degree days6,200
Land price / acre$1,397

Regulatory climate

Favorablestate posture · as of 2026-08

Public-power incentives; DC-friendly.

DC tax incentiveYes

Incentive detail: ImagiNE Nebraska Act: sales tax exemption on DC equipment; investment tax credits.

Site location

◆ Loading map…
≥ 7560–7540–60≤ 40
This site + 8 nearby

Get alerts

Track Chadron Substation

Get an email when its DC-readiness score, available capacity, or interconnection-queue status changes.

No spam. Just the alerts you asked for.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
30
Speed to power20%
52
Fiber connectivity12%
64
Energy cost10%
50
Water risk7%
60
Natural hazard6%
72
Buildability7%
50
Labor market4%
50
DC cluster4%
20
Land / acreage3%
38
Construction cost3%
50
Gas pipeline2%
10
Tax incentive1%
100
Climate / cooling1%
75

Nearby comparable sites

Other scored datacenter candidate sites in Dawes County, ranked by DC Readiness.

Sites near Chadron Substation
SiteTypeVoltageCapacityQueue waitScore
WAYSIDESubstation-Adjacent230 kV300 MW3.3 yrs59.3
UNKNOWN132442Substation-Adjacent115 kV100 MW3.3 yrs54.9
UNKNOWN132446Substation-Adjacent115 kV100 MW3.3 yrs54.9
UNKNOWN132448Substation-Adjacent115 kV100 MW3.3 yrs53.7
Crawford Fire HallIndustrial——3.3 yrs49.0
821 Morehead StreetIndustrial——3.3 yrs49.0
Industrial area of ChadronIndustrial——3.3 yrs49.0
216 Elm StreetIndustrial——3.3 yrs49.0

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for Chadron Substation, Dawes County. Pro and Enterprise plans unlock the full 147,272-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.