DC Readiness
63.2
Good / 100

EC Near J E Corette Plant is a greenfield datacenter candidate site in Yellowstone County, Montana, interconnecting through SPP. It screens at 63.2/100 DC Readiness and a 1.1 yrs average interconnection-queue wait.

Power & interconnection

LMP zoneSPP_NORTH
Wholesale LMP$21.13/MWh
Utility commercial rate0.10¢/kWh
UtilityYELLOWSTONE VALLEY ELEC CO-OPcooperativefavorable to large load · state default

Speed to power

Interconnection outlookFavorable
≈ 0.5 yrs typical interconnection wait

Shorter queues and healthier completion here — a faster path to energization than the national norm.

ISO / RTO regionSPP
Queue depth35
Avg queue wait1.1 yrs
Recent queue wait0.5 yrs
Completion rate16%
Withdrawal rate84%

Connectivity

Nearest IXPCogent Billings
IXP distance2.2 mi
Fiber providers13
Fiber coverage32.8%
Nearest cloud providerGCP
Nearest cloud regionus-west3
Cloud region distance380.7 mi

Site characteristics

Site typeGreenfield
Land contactYellowstone County Assessor
Land owner typeprivate
Buildability40.0/100
Land cover (NLCD)Evergreen Forest
Former usenear retired coal plant (10km)

Risk & environment

Environmental constraintLow (30/100)
Flood zoneZone X
Water stress (WRI)2.20
Wetlands (NWI)Clear
Critical habitatClear
Superfund nearbyPresent
Superfund siteYELLOWSTONE OIL SPILL
Hazard sub-score78/100
Construction cost index86.6 (avg 100)

Location context

Nearest datacenterCogent Billings
DC distance2.2 mi
Nearest rail2.1 mi
Nearest gas pipeline2.0 mi
Nearest fiber route173.5 mi
County hazard (FEMA NRI)Very Low (12)
DC tax incentiveYes (property_tax_abatement)
Commercial electricity10.16¢/kWh
Industrial electricity9.50¢/kWh
Cooling degree days400
Heating degree days7,600
Land price / acre$1,216

Regulatory climate

Moderatestate posture · as of 2026-08

No notable statewide DC restriction on record; confirm local zoning and utility tariffs.

DC tax incentiveNo / suspended

Incentive detail: New/expanding industry tax abatement available for DC construction.

Site location

◆ Loading map…
≥ 7560–7540–60≤ 40
This site + 8 nearby

Get alerts

Track EC Near J E Corette Plant

Get an email when its DC-readiness score, available capacity, or interconnection-queue status changes.

No spam. Just the alerts you asked for.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
30
Speed to power20%
62
Fiber connectivity12%
82
Energy cost10%
90
Water risk7%
68
Natural hazard6%
78
Buildability7%
40
Labor market4%
50
DC cluster4%
100
Land / acreage3%
54
Construction cost3%
78
Gas pipeline2%
94
Tax incentive1%
100
Climate / cooling1%
100

Nearby comparable sites

Other scored datacenter candidate sites in Yellowstone County, ranked by DC Readiness.

Sites near EC Near J E Corette Plant
SiteTypeVoltageCapacityQueue waitScore
EC Coal Yellowstone CountyGreenfield——1.1 yrs66.7
BILLINGSSubstation-Adjacent230 kV300 MW3.3 yrs66.6
EC Near J E Corette PlantGreenfield——1.1 yrs65.5
UNKNOWN202569Substation-Adjacent230 kV300 MW3.3 yrs65.4
EC Near J E Corette PlantGreenfield——1.1 yrs64.9
SHOREY ROADSubstation-Adjacent230 kV300 MW3.3 yrs64.9
ALKALI CREEKSubstation-Adjacent230 kV300 MW3.3 yrs64.9
EC Near J E Corette PlantGreenfield——1.1 yrs64.0

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for EC Near J E Corette Plant, Yellowstone County. Pro and Enterprise plans unlock the full 147,272-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.