Datacenter Sites in PANOLA, Mississippi
PANOLA has 66 scored datacenter candidate sites averaging 55.1/100 DC Readiness, with a catalogued aggregate of 2,992 MW. FEMA rates local natural-hazard risk as "Relatively High". The county has a datacenter tax incentive on record.
66
Candidate sites
55.1/100
Avg DC Readiness
2,992 MW
Catalogued capacity
theoretical aggregate
Relatively High
Hazard rating
Site-selection context for PANOLA
Yessales_tax_exemption
Datacenter tax incentive
11.60¢/kWh
Commercial electricity
7.22¢/kWh
Industrial electricity
3
Fiber providers
Low
Water stress
$3,142
Land price / acre
2,400
Cooling degree days
2,400
Heating degree days
64°F
Mean annual temp
Incentive detail: Sales tax exemption on DC equipment for $50M+ investments; fee-in-lieu of property tax.
By site type
Top datacenter sites in PANOLA
| Site | Type | Voltage | Capacity | Queue wait | Score |
|---|---|---|---|---|---|
| EC Near Batesville Generation Facility | Greenfield | — | — | 1.4 yrs | 61.5 |
| EC Near Batesville Generation Facility | Greenfield | — | — | 1.4 yrs | 61.3 |
| EC Near Batesville Generation Facility | Greenfield | — | — | 1.4 yrs | 60.9 |
| EC Near Batesville Generation Facility | Greenfield | — | — | 1.4 yrs | 60.4 |
| EC Near Batesville Generation Facility | Greenfield | — | — | 1.4 yrs | 60.2 |
| UNKNOWN110928 | Substation-Adjacent | 230 kV | 300 MW | 2.8 yrs | 59.5 |
| EC FFE Panola County | Greenfield | — | — | 1.4 yrs | 59.2 |
| EC Near Batesville Generation Facility | Greenfield | — | — | 1.4 yrs | 58.5 |
| EC Near Batesville Generation Facility | Greenfield | — | — | 1.4 yrs | 58.2 |
| UNKNOWN110761 | Substation-Adjacent | 230 kV | 300 MW | 2.8 yrs | 57.9 |
| EC Near Batesville Generation Facility | Greenfield | — | — | 1.4 yrs | 57.8 |
| EC Near Batesville Generation Facility | Greenfield | — | — | 1.4 yrs | 57.8 |
| EC Near Batesville Generation Facility | Greenfield | — | — | 1.4 yrs | 57.7 |
| TAP149958 | Substation-Adjacent | 161 kV | 100 MW | 2.8 yrs | 54.3 |
| UNKNOWN111288 | Substation-Adjacent | 161 kV | 100 MW | 2.8 yrs | 54.3 |
| UNKNOWN169491 | Substation-Adjacent | 161 kV | 100 MW | 2.8 yrs | 54.3 |
| EC Near Batesville Generation Facility | Greenfield | — | — | 1.4 yrs | 54.2 |
| UNKNOWN110930 | Substation-Adjacent | 115 kV | 100 MW | 2.8 yrs | 53.6 |
| N. SARDIS | Substation-Adjacent | 115 kV | 100 MW | 2.8 yrs | 53.6 |
| Mine Site | Former Mine | — | — | 2.8 yrs | 51.4 |
| Mine Site | Former Mine | — | — | 2.8 yrs | 51.4 |
| Mine Site | Former Mine | — | — | 2.8 yrs | 51.3 |
| Mine Site | Former Mine | — | — | 2.8 yrs | 51.3 |
| Old Panola Mills Building | Industrial | — | — | 2.8 yrs | 51.3 |
| Mine Site | Former Mine | — | — | 2.8 yrs | 51.0 |
PANOLA datacenter FAQ
- How many datacenter sites are in PANOLA?
- 66 scored datacenter candidate sites, averaging 55.1/100 DC Readiness.
- Does PANOLA offer datacenter tax incentives?
- Sales tax exemption on DC equipment for $50M+ investments; fee-in-lieu of property tax.
- What is the natural-hazard risk in PANOLA?
- FEMA's National Risk Index rates PANOLA as "Relatively High" (score 45).
- What are industrial electricity rates in PANOLA?
- Average industrial electricity is 7.22¢/kWh and commercial is 11.60¢/kWh in PANOLA.
Dataset updated . Screening estimates derived from public data sources.
Go deeper than the public screen
This page shows a public slice of the GridCensus dataset for PANOLA, Mississippi. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.