UNKNOWN172452 is a substation-adjacent datacenter candidate site in Lenawee County, Michigan, interconnecting through PJM. It screens at 57.4/100 DC Readiness with a catalogued 100 MW of candidate capacity and a 3.8 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationUNKNOWN172452
Substation distance0.0 mi
Substation voltage138 kV
Available capacity100 MW
UtilityCONSUMERS ENERGY COinvestor ownedfavorable to large load · terms ≥ 100 MWLarge-load contract terms; MI DC sales/use-tax exemption (2025) · 15 yr

Speed to power

Interconnection outlookModerate
≈ 3.8 yrs typical interconnection wait

Middle-of-the-pack interconnection conditions for this grid.

ISO / RTO regionPJM
Queue depth17
Avg queue wait3.8 yrs

Connectivity

Nearest IXPSynergy Fiber
IXP distance28.7 mi
Fiber providers13
Fiber coverage72.7%

Site characteristics

Risk & environment

Environmental constraintNone (0/100)
Water stress (WRI)Low
Wetlands (NWI)—
Critical habitat—
Superfund nearby—
Hazard sub-score75/100

Location context

Nearest datacenterDatacenter 11815482844
DC distance21.2 mi
County hazard (FEMA NRI)Relatively Moderate (25)
DC tax incentiveYes (property_tax_exemption)
Commercial electricity11.33¢/kWh
Industrial electricity4.61¢/kWh
Cooling degree days700
Heating degree days6,600
Land price / acre$5,766

Regulatory climate

Moderatestate posture · as of 2026-08

No notable statewide DC restriction on record; confirm local zoning and utility tariffs.

DC tax incentiveNo / suspended

Incentive detail: Personal property tax exemption for eligible DC equipment; MEGA tax credits.

Site location

◆ Loading map…
≥ 7560–7540–60≤ 40
This site + 8 nearby

Get alerts

Track UNKNOWN172452

Get an email when its DC-readiness score, available capacity, or interconnection-queue status changes.

No spam. Just the alerts you asked for.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
58
Speed to power20%
37
Fiber connectivity12%
72
Energy cost10%
50
Water risk7%
94
Natural hazard6%
75
Buildability7%
60
Labor market4%
50
DC cluster4%
60
Land / acreage3%
43
Construction cost3%
50
Gas pipeline2%
10
Tax incentive1%
100
Climate / cooling1%
90

Nearby comparable sites

Other scored datacenter candidate sites in Lenawee County, ranked by DC Readiness.

Sites near UNKNOWN172452
SiteTypeVoltageCapacityQueue waitScore
EC FFE Lenawee CountyGreenfield——2.2 yrs61.9
TAP137295Substation-Adjacent138 kV100 MW3.8 yrs58.4
UNKNOWN130371Substation-Adjacent138 kV100 MW3.8 yrs58.2
MOROCCOSubstation-Adjacent138 kV100 MW3.8 yrs58.1
TAP140010Substation-Adjacent138 kV100 MW3.8 yrs58.1
Greenfield (ALLEN JUNCTION - UNKNOWN171366)Greenfield345 kV600 MW3.8 yrs57.7
BEECHERSubstation-Adjacent138 kV100 MW3.8 yrs57.4
UNKNOWN130222Substation-Adjacent138 kV100 MW3.8 yrs57.3

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.