Hillsdale

Brownfield

Hillsdale County, Michigan · PJM

DC Readiness
53.2
Fair / 100

Hillsdale is a brownfield datacenter candidate site in Hillsdale County, Michigan, interconnecting through PJM. It screens at 53.2/100 DC Readiness with a catalogued 17 MW of candidate capacity and a 2.2 yrs average interconnection-queue wait.

Power & interconnection

Available capacity17 MW
LMP zonePJM_ATSI
Wholesale LMP$42.97/MWh
Utility commercial rate0.10¢/kWh

Speed to power

ISO / RTO regionPJM
Queue depth11
Avg queue wait2.2 yrs
Recent queue wait2.2 yrs
Completion rate20%
Withdrawal rate80%

Connectivity

Nearest IXPSynergy Fiber
IXP distance51.4 mi
Fiber providers9
Fiber coverage21.9%
Nearest cloud providerAzure
Nearest cloud regionnorthcentralus
Cloud region distance154.2 mi

Site characteristics

Site typeBrownfield
Parcel ownerHillsdale Board of Public Wks
Land owner typeprivate
Buildability90.0/100
Land cover (NLCD)Developed, Open Space
Former useoil
Existing capacity17 MW
Retirement date2018-06-01

Risk & environment

Flood zoneZone X
Water stress (WRI)0.30
Wetlands (NWI)Clear
Critical habitatClear
Superfund nearbyPresent
Superfund siteDONALD R LAVAUN D TRUST
Hazard sub-score65/100
Construction cost index64.6 (avg 100)

Location context

Nearest datacenterLagrange CO
DC distance44.9 mi
Nearest rail1.1 mi
Nearest gas pipeline16.6 mi
Nearest fiber route162.8 mi
County hazard (FEMA NRI)Relatively Moderate (25)
DC tax incentiveYes (property_tax_exemption)
Commercial electricity9.60¢/kWh
Industrial electricity4.56¢/kWh
Cooling degree days700
Heating degree days6,600
Land price / acre$5,493

Incentive detail: Personal property tax exemption for eligible DC equipment; MEGA tax credits.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
25
Speed to power15%
44
Fiber connectivity12%
12
Energy cost10%
81
Water risk8%
94
Natural hazard8%
65
Buildability7%
90
Labor market4%
50
DC cluster4%
45
Land / acreage3%
55
Construction cost3%
96
Gas pipeline2%
47
Tax incentive2%
100
Climate / cooling2%
90

Nearby comparable sites

Other scored datacenter candidate sites in Hillsdale County, ranked by DC Readiness.

Sites near Hillsdale
SiteTypeVoltageCapacityQueue waitScore
UNKNOWN128594Substation-Adjacent138 kV100 MW2.2 yrs65.3
ENDICOTT STATIONSubstation-Adjacent138 kV100 MW2.2 yrs62.7
OZ HillsdaleGreenfield2.2 yrs61.1
EC Coal Hillsdale CountyGreenfield2.2 yrs61.0
Greenfield (ENDICOTT STATION - UNKNOWN1285)Greenfield138 kV100 MW2.2 yrs60.2
Greenfield (ENDICOTT STATION - UNKNOWN1456)Greenfield138 kV100 MW2.2 yrs60.1
EC Coal Hillsdale CountyGreenfield2.2 yrs60.0
EC Coal Hillsdale CountyGreenfield2.2 yrs59.9

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for Hillsdale, Hillsdale County. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.