DC Readiness
56.2
Good / 100

Greenfield (BUXTON - SCOBIE POND 345KV) is a greenfield datacenter candidate site in York County, Maine, interconnecting through ISO-NE. It screens at 56.2/100 DC Readiness with a catalogued 600 MW of candidate capacity and a 3.9 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationBUXTON
Substation voltage345 kV
Available capacity600 MW

Speed to power

ISO / RTO regionISO-NE
Queue depth83
Avg queue wait3.9 yrs

Connectivity

Nearest IXPFirstLight Regen Hut
IXP distance17.4 mi
Fiber providers9
Fiber coverage52.2%

Site characteristics

Site typeGreenfield
Land contactYork County County Assessor

Risk & environment

Water stress (WRI)Low
Wetlands (NWI)
Critical habitat
Superfund nearby
Hazard sub-score85/100

Location context

Nearest datacenterFirstLight Data Center
DC distance19.3 mi
County hazard (FEMA NRI)Relatively Low (15)
DC tax incentiveNo
Commercial electricity13.95¢/kWh
Industrial electricity12.34¢/kWh
Cooling degree days300
Heating degree days7,500
Land price / acre$7,643

Site location

◆ Loading map…
≥ 7560–7540–60≤ 40
This site + 8 nearby

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
59
Speed to power15%
34
Fiber connectivity12%
54
Energy cost10%
50
Water risk8%
96
Natural hazard8%
85
Buildability7%
50
Labor market4%
50
DC cluster4%
60
Land / acreage3%
51
Construction cost3%
50
Gas pipeline2%
10
Tax incentive2%
0
Climate / cooling2%
100

Nearby comparable sites

Other scored datacenter candidate sites in York County, ranked by DC Readiness.

Sites near Greenfield (BUXTON - SCOBIE POND 345KV)
SiteTypeVoltageCapacityQueue waitScore
OZ YorkGreenfield3.5 yrs62.7
MAGUIRE ROADSubstation-Adjacent345 kV600 MW3.9 yrs61.0
UNKNOWN136751Substation-Adjacent115 kV100 MW3.9 yrs58.2
LOUDENSubstation-Adjacent115 kV100 MW3.9 yrs57.8
BIDDEFORD IPSubstation-Adjacent115 kV100 MW3.9 yrs56.5
TAP136665Substation-Adjacent115 kV100 MW3.9 yrs56.3
WATERBOROSubstation-Adjacent115 kV100 MW3.9 yrs55.5
TAP136666Substation-Adjacent115 kV100 MW3.9 yrs55.1

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for Greenfield (BUXTON - SCOBIE POND 345KV), York County. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.