Skip to content
Gridcensus

UNKNOWN168670

Substation-Adjacent

Stevens, Kansas · SPP

DC Readiness
52.6
Fair / 100

UNKNOWN168670 is a substation-adjacent datacenter candidate site in Stevens, Kansas, interconnecting through SPP. It screens at 52.6/100 DC Readiness with a catalogued 50 MW of candidate capacity and a 3.3 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationUNKNOWN168670
Nearest grid bottleneckTP1241_33286 · 80 km (SPP)
Substation distance0.0 mi
Substation voltage69 kV
Available capacity50 MW
UtilityPIONEER ELECTRIC COOP, INC - (KS)cooperativefavorable to large load · state default

Speed to power

Interconnection outlookModerate
≈ 3.3 yrs typical interconnection wait

Middle-of-the-pack interconnection conditions for this grid.

ISO / RTO regionSPP
Queue depth64
Avg queue wait3.3 yrs

Connectivity

Nearest IXPAmarillo Petroleum Building
IXP distance146.4 mi
Fiber providers1
Fiber coverage80.8%

Site characteristics

Risk & environment

Environmental constraintNone (0/100)
Water stress (WRI)Medium-High
Wetlands (NWI)
Critical habitat
Superfund nearby
Hazard sub-score65/100

Location context

Nearest datacenterSC DC
DC distance144.3 mi
County hazard (FEMA NRI)Relatively High (35)
DC tax incentiveYes (property_tax_exemption)
Commercial electricity11.47¢/kWh
Industrial electricity9.88¢/kWh
Cooling degree days1,400
Heating degree days5,000
Land price / acre$1,792

Regulatory climate

Moderatestate posture · as of 2026-08

No notable statewide DC restriction on record; confirm local zoning and utility tariffs.

DC tax incentiveNo / suspended

Incentive detail: PEAK program payroll tax incentives; IRB property tax exemptions available.

Site location

◆ Loading map…
≥ 7560–7540–60≤ 40
This site + 8 nearby

Get alerts

Track UNKNOWN168670

Get an email when its DC-readiness score, available capacity, or interconnection-queue status changes.

No spam. Just the alerts you asked for.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
46
Speed to power20%
54
Fiber connectivity12%
68
Energy cost10%
50
Water risk7%
52
Natural hazard6%
65
Buildability7%
60
Labor market4%
50
DC cluster4%
20
Land / acreage3%
52
Construction cost3%
50
Gas pipeline2%
10
Tax incentive1%
100
Climate / cooling1%
55

Nearby comparable sites

Other scored datacenter candidate sites in Stevens, ranked by DC Readiness.

Sites near UNKNOWN168670
SiteTypeVoltageCapacityQueue waitScore
Hugoton 1Brownfield69 kV1 MW3.5 yrs59.5
EC Near Hugoton 1Greenfield3.5 yrs59.4
EC Near Hugoton 1Greenfield3.5 yrs59.1
EC Near Hugoton 1Greenfield3.5 yrs58.8
EC Near Hugoton 1Greenfield3.5 yrs58.7
EC Near Hugoton 1Greenfield3.5 yrs58.3
EC Near Hugoton 1Greenfield3.5 yrs57.7
EC Near Hugoton 1Greenfield3.5 yrs57.6

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for UNKNOWN168670, Stevens. Pro and Enterprise plans unlock the full 147,272-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.