Skip to content
Gridcensus

UNKNOWN119865

Substation-Adjacent

Reno, Kansas · SPP

DC Readiness
55.6
Good / 100

UNKNOWN119865 is a substation-adjacent datacenter candidate site in Reno, Kansas, interconnecting through SPP. It screens at 55.6/100 DC Readiness with a catalogued 100 MW of candidate capacity and a 3.3 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationUNKNOWN119865
Nearest grid bottleneckTP1136_32015 · 82 km (SPP)
Substation distance0.0 mi
Substation voltage115 kV
Available capacity100 MW
UtilityEVERGY KANSAS SOUTH, INCinvestor ownedfavorable to large load · terms ≥ 75 MWLarge Load Power Service (LLPS, ≥75 MW) · 80% min take · 12 yr

Speed to power

Interconnection outlookModerate
≈ 3.3 yrs typical interconnection wait

Middle-of-the-pack interconnection conditions for this grid.

ISO / RTO regionSPP
Queue depth64
Avg queue wait3.3 yrs

Connectivity

Nearest IXPBeloit-NOC
IXP distance97.9 mi
Fiber providers6
Fiber coverage84.3%

Site characteristics

Risk & environment

Environmental constraintNone (0/100)
Water stress (WRI)Medium-High
Wetlands (NWI)
Critical habitat
Superfund nearby
Hazard sub-score65/100

Location context

Nearest datacenterSC DC
DC distance55.4 mi
County hazard (FEMA NRI)Relatively High (35)
DC tax incentiveYes (property_tax_exemption)
Commercial electricity10.97¢/kWh
Industrial electricity8.41¢/kWh
Cooling degree days1,400
Heating degree days5,000
Land price / acre$2,641

Regulatory climate

Moderatestate posture · as of 2026-08

No notable statewide DC restriction on record; confirm local zoning and utility tariffs.

DC tax incentiveNo / suspended

Incentive detail: PEAK program payroll tax incentives; IRB property tax exemptions available.

Site location

◆ Loading map…
≥ 7560–7540–60≤ 40
This site + 8 nearby

Get alerts

Track UNKNOWN119865

Get an email when its DC-readiness score, available capacity, or interconnection-queue status changes.

No spam. Just the alerts you asked for.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
56
Speed to power20%
54
Fiber connectivity12%
70
Energy cost10%
50
Water risk7%
52
Natural hazard6%
65
Buildability7%
60
Labor market4%
50
DC cluster4%
40
Land / acreage3%
52
Construction cost3%
50
Gas pipeline2%
10
Tax incentive1%
100
Climate / cooling1%
55

Nearby comparable sites

Other scored datacenter candidate sites in Reno, ranked by DC Readiness.

Sites near UNKNOWN119865
SiteTypeVoltageCapacityQueue waitScore
UNKNOWN118040Substation-Adjacent230 kV300 MW3.3 yrs61.3
OZ RenoGreenfield3.5 yrs61.2
RENOSubstation-Adjacent345 kV600 MW3.3 yrs61.2
EC Near Hutchinson Energy CenterGreenfield3.5 yrs60.1
EC Near Hutchinson Energy CenterGreenfield3.5 yrs59.7
EC Near Hutchinson Energy CenterGreenfield3.5 yrs58.7
EC Near Hutchinson Energy CenterGreenfield3.5 yrs58.7
EC Near Hutchinson Energy CenterGreenfield3.5 yrs58.5

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.