Skip to content
Gridcensus

UNKNOWN173427

Substation-Adjacent

Miami, Kansas · SPP

DC Readiness
61.0
Good / 100

UNKNOWN173427 is a substation-adjacent datacenter candidate site in Miami, Kansas, interconnecting through SPP. It screens at 61.0/100 DC Readiness with a catalogued 100 MW of candidate capacity and a 3.3 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationUNKNOWN173427
Nearest grid bottleneckTMP338_28287 · 35 km (SPP)
Substation distance0.0 mi
Substation voltage161 kV
Available capacity100 MW
UtilityHEARTLAND RURAL ELEC COOP, INCnot available

Speed to power

Interconnection outlookModerate
≈ 3.3 yrs typical interconnection wait

Middle-of-the-pack interconnection conditions for this grid.

ISO / RTO regionSPP
Queue depth64
Avg queue wait3.3 yrs

Connectivity

Nearest IXPQTS Overland Park (OVP1)
IXP distance28.0 mi
Fiber providers12
Fiber coverage67.5%

Site characteristics

Former usegas
Existing capacity639 MW

Risk & environment

Environmental constraintNone (0/100)
Water stress (WRI)Medium-High
Wetlands (NWI)
Critical habitat
Superfund nearby
Hazard sub-score65/100

Location context

Nearest datacenterU.S. Bank National Data Process Center
DC distance28.0 mi
County hazard (FEMA NRI)Relatively High (35)
DC tax incentiveYes (property_tax_exemption)
Commercial electricity10.75¢/kWh
Industrial electricity9.74¢/kWh
Cooling degree days1,400
Heating degree days5,000
Land price / acre$4,190

Regulatory climate

Moderatestate posture · as of 2026-08

No notable statewide DC restriction on record; confirm local zoning and utility tariffs.

DC tax incentiveNo / suspended

Incentive detail: PEAK program payroll tax incentives; IRB property tax exemptions available.

Site location

◆ Loading map…
≥ 7560–7540–60≤ 40
This site + 8 nearby

Get alerts

Track UNKNOWN173427

Get an email when its DC-readiness score, available capacity, or interconnection-queue status changes.

No spam. Just the alerts you asked for.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
60
Speed to power20%
73
Fiber connectivity12%
72
Energy cost10%
50
Water risk7%
52
Natural hazard6%
65
Buildability7%
60
Labor market4%
50
DC cluster4%
60
Land / acreage3%
52
Construction cost3%
50
Gas pipeline2%
10
Tax incentive1%
100
Climate / cooling1%
55

Nearby comparable sites

Other scored datacenter candidate sites in Miami, ranked by DC Readiness.

Sites near UNKNOWN173427
SiteTypeVoltageCapacityQueue waitScore
EC Near OsawatomieGreenfield3.5 yrs62.3
EC Near OsawatomieGreenfield3.5 yrs60.8
EC Near OsawatomieGreenfield3.5 yrs60.8
EC Near OsawatomieGreenfield3.5 yrs60.5
EC Near OsawatomieGreenfield3.5 yrs60.0
EC Near OsawatomieGreenfield3.5 yrs60.0
EC Near OsawatomieGreenfield3.5 yrs59.5
UNKNOWN118176Substation-Adjacent161 kV100 MW3.3 yrs59.4

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for UNKNOWN173427, Miami. Pro and Enterprise plans unlock the full 147,272-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.