EC Coal Pulaski County

Greenfield

Pulaski County, Indiana · PJM

DC Readiness
52.6
Fair / 100

EC Coal Pulaski County is a greenfield datacenter candidate site in Pulaski County, Indiana, interconnecting through PJM. It screens at 52.6/100 DC Readiness and a 3.0 yrs average interconnection-queue wait.

Power & interconnection

LMP zonePJM_DUKE
Wholesale LMP$41.74/MWh
Utility commercial rate0.14¢/kWh

Speed to power

ISO / RTO regionPJM
Queue depth56
Avg queue wait3.0 yrs
Recent queue wait4.2 yrs
Completion rate14%
Withdrawal rate87%

Connectivity

Nearest IXPAunalytics South Bend Datacenter (AUSB)
IXP distance46.4 mi
Fiber providers7
Fiber coverage53.5%
Nearest cloud providerAzure
Nearest cloud regionnorthcentralus
Cloud region distance69.4 mi

Site characteristics

Site typeGreenfield
Parcel ownerNORTHERN INDIANA PUB SERV CO
Land owner typeprivate
Buildability65.0/100
Land cover (NLCD)Cultivated Crops
Former usecoal adjacent

Risk & environment

Flood zoneZone X
Water stress (WRI)0.50
Wetlands (NWI)Clear
Critical habitatClear
Superfund nearbyClear
Hazard sub-score68/100
Construction cost index63.0 (avg 100)

Location context

Nearest datacenterAmazon AWS Data Center
DC distance41.5 mi
Nearest rail6.5 mi
Nearest gas pipeline0.0 mi
Nearest fiber route76.5 mi
County hazard (FEMA NRI)Relatively Moderate (32)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity14.42¢/kWh
Industrial electricity8.35¢/kWh
Cooling degree days1,000
Heating degree days5,500
Land price / acre$9,173

Incentive detail: Sales tax exemption on DC equipment for $750M+/$400M+ investments; EDGE credits up to 100% of payroll taxes.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
30
Speed to power15%
35
Fiber connectivity12%
20
Energy cost10%
84
Water risk8%
86
Natural hazard8%
68
Buildability7%
65
Labor market4%
50
DC cluster4%
50
Land / acreage3%
40
Construction cost3%
98
Gas pipeline2%
100
Tax incentive2%
100
Climate / cooling2%
75

Nearby comparable sites

Other scored datacenter candidate sites in Pulaski County, ranked by DC Readiness.

Sites near EC Coal Pulaski County
SiteTypeVoltageCapacityQueue waitScore
Greenfield (OLIVE - REYNOLDS)Greenfield345 kV600 MW2.2 yrs68.0
Greenfield (OLIVE - REYNOLDS)Greenfield345 kV600 MW2.2 yrs66.6
Greenfield (OLIVE - REYNOLDS)Greenfield345 kV600 MW2.2 yrs66.1
Greenfield (UNKNOWN122924 - TAP138139)Greenfield138 kV100 MW3.0 yrs59.6
EC Coal Pulaski CountyGreenfield3.0 yrs57.2
Greenfield (UNKNOWN122641 - BURR OAK)Greenfield138 kV100 MW3.0 yrs57.0
Greenfield (UNKNOWN122641 - MONTICELLO)Greenfield138 kV100 MW3.0 yrs56.9
Greenfield (UNKNOWN122641 - MONTICELLO)Greenfield138 kV100 MW3.0 yrs56.4

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for EC Coal Pulaski County, Pulaski County. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.