Skip to content
Gridcensus

UNKNOWN122641

Substation-Adjacent

Pulaski County, Indiana · PJM

DC Readiness
53.0
Fair / 100

UNKNOWN122641 is a substation-adjacent datacenter candidate site in Pulaski County, Indiana, interconnecting through PJM. It screens at 53.0/100 DC Readiness with a catalogued 100 MW of candidate capacity and a 3.8 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationUNKNOWN122641
Substation distance0.0 mi
Substation voltage138 kV
Available capacity100 MW

Speed to power

ISO / RTO regionPJM
Queue depth62
Avg queue wait3.8 yrs

Connectivity

Nearest IXPAunalytics South Bend Datacenter (AUSB)
IXP distance44.6 mi
Fiber providers10
Fiber coverage71.6%

Site characteristics

Risk & environment

Water stress (WRI)Low
Wetlands (NWI)
Critical habitat
Superfund nearby
Hazard sub-score68/100

Location context

Nearest datacenterAmazon AWS Data Center
DC distance42.4 mi
County hazard (FEMA NRI)Relatively Moderate (32)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity14.42¢/kWh
Industrial electricity8.35¢/kWh
Cooling degree days1,000
Heating degree days5,500
Land price / acre$9,173

Incentive detail: Sales tax exemption on DC equipment for $750M+/$400M+ investments; EDGE credits up to 100% of payroll taxes.

Site location

◆ Loading map…
≥ 7560–7540–60≤ 40
This site + 8 nearby

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
58
Speed to power15%
33
Fiber connectivity12%
38
Energy cost10%
50
Water risk8%
90
Natural hazard8%
68
Buildability7%
60
Labor market4%
50
DC cluster4%
40
Land / acreage3%
42
Construction cost3%
50
Gas pipeline2%
10
Tax incentive2%
100
Climate / cooling2%
75

Nearby comparable sites

Other scored datacenter candidate sites in Pulaski County, ranked by DC Readiness.

Sites near UNKNOWN122641
SiteTypeVoltageCapacityQueue waitScore
EC Coal Pulaski CountyGreenfield3.0 yrs58.1
EC Coal Pulaski CountyGreenfield3.0 yrs57.8
FRANCESVILLE DRAIN TILE CORP. (ALL OTHER PLASTICS PRODUCT MANUFACTURING)Manufacturing3.5 yrs52.9
VULCAN MATERIALS CO. (CUT STONE AND STONE PRODUCT MANUFACTURING)Manufacturing3.5 yrs52.9
BNK, INC. (NOT AVAILABLE)Manufacturing3.5 yrs52.5
METAL FAB ENGINEERING (IRON AND STEEL MILLS)Manufacturing3.5 yrs52.5
KRYSTIL KLEAR FILTRATION (ALL OTHER INDUSTRIAL MACHINERY MANUFACTURING)Manufacturing3.5 yrs52.2
KOVA AG PRODUCTS, INC. (FERTILIZER (MIXING ONLY) MANUFACTURING)Manufacturing3.5 yrs51.9

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for UNKNOWN122641, Pulaski County. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.