Skip to content
Gridcensus

Greenfield (UNKNOWN124912 - COLUMBUS (345K)

Greenfield

BARTHOLOMEW, Indiana · MISO

DC Readiness
54.6
Fair / 100

At a glance

Greenfield (UNKNOWN124912 - COLUMBUS (345K) is a greenfield datacenter candidate site in BARTHOLOMEW, Indiana, scoring 54.6/100 DC Readiness — 91st of 109 scored sites in the county. Its nearest substation is UNKNOWN124912. It sits in the MISO grid region and the DUKE ENERGY INDIANA, LLC service territory, where interconnection has averaged 3.0 years from request to operation. GridCensus catalogs 100 MW of candidate capacity here.

Power & interconnection

Nearest substationUNKNOWN124912
Substation voltage138 kV
Available capacity100 MW
UtilityDUKE ENERGY INDIANA, LLCinvestor ownedfavorable to large load · terms ≥ 100 MW

Speed to power

Interconnection outlookModerate
≈ 4.9 yrs typical interconnection wait

Middle-of-the-pack interconnection conditions for this grid.

ISO / RTO regionMISO
Queue depth170
Avg queue wait3.0 yrs
Recent queue wait4.9 yrs
Completion rate14%
Withdrawal rate87%

Connectivity

Nearest IXPDartPoints Columbus, IN - CLU1
IXP distance7.0 mi
Fiber providers9
Fiber coverage65.8%

Site characteristics

Site typeGreenfield

Risk & environment

Environmental constraintNone (0/100)
Water stress (WRI)Low
Wetlands (NWI)—
Critical habitat—
Superfund nearby—
Hazard sub-score68/100

Location context

Nearest datacenterDartPoints Columbus, IN - CLU1
DC distance7.0 mi
County hazard (FEMA NRI)Relatively Moderate (32)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity11.87¢/kWh
Industrial electricity8.84¢/kWh
Cooling degree days1,000
Heating degree days5,500
Land price / acre$6,180

Regulatory climate

Moderatestate posture · as of 2026-08

No notable statewide DC restriction on record; confirm local zoning and utility tariffs.

DC tax incentiveNo / suspended

Incentive detail: Sales tax exemption on DC equipment for $750M+/$400M+ investments; EDGE credits up to 100% of payroll taxes.

Site location

◆ Loading map…
≥ 7560–7540–60≤ 40
This site + 8 nearby

Get alerts

Track Greenfield (UNKNOWN124912 - COLUMBUS (345K)

Get an email when its DC-readiness score, available capacity, or interconnection-queue status changes.

No spam. Just the alerts you asked for.

How does Greenfield (UNKNOWN124912 - COLUMBUS (345K) compare with other sites in BARTHOLOMEW?

Greenfield (UNKNOWN124912 - COLUMBUS (345K) ranks 91st of 109 scored candidate sites in BARTHOLOMEW. Its 54.6/100 is roughly in line with the county average of 55.7. It is roughly in line with the Indiana average of 54.0 and roughly in line with the national average of 53.2.

Against the Indiana average, its strongest sub-score is fiber connectivity (86 vs 79) and its weakest is power availability (30 vs 33). Power and speed to power each carry 20% of the composite score, fiber 12%, water 7% and hazard 6%.

How close is Greenfield (UNKNOWN124912 - COLUMBUS (345K) to power, fiber and other datacenters?

The nearest mapped substation, UNKNOWN124912, is the closest grid connection point on record and operates at 138 kV. The nearest located transmission bottleneck is CIN23031_DRESSER_DRESS08ALE13_2_1 (MISO), 90 miles away. For connectivity, the nearest internet exchange facility is DartPoints Columbus, IN - CLU1 at 7 miles. 9 fiber providers report service at the location in FCC broadband data. The closest operating datacenter on record is DartPoints Columbus, IN - CLU1, 7 miles away.

What are the flood, water and hazard risks at Greenfield (UNKNOWN124912 - COLUMBUS (345K)?

At the county level, FEMA's National Risk Index rates BARTHOLOMEW "Relatively Moderate".

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
30
Speed to power20%
47
Fiber connectivity12%
86
Energy cost10%
50
Water risk7%
90
Natural hazard6%
68
Buildability7%
50
Labor market4%
50
DC cluster4%
80
Land / acreage3%
42
Construction cost3%
50
Gas pipeline2%
10
Tax incentive1%
100
Climate / cooling1%
75

Nearby comparable sites

Other scored datacenter candidate sites in BARTHOLOMEW, ranked by DC Readiness.

Sites near Greenfield (UNKNOWN124912 - COLUMBUS (345K)
SiteTypeVoltageCapacityQueue waitScore
COLUMBUS (345KV)Substation-Adjacent345 kV600 MW3.0 yrs68.2
OZ BartholomewGreenfield——3.0 yrs65.6
COLUMBUS DENOIS CREEKSubstation-Adjacent230 kV300 MW3.0 yrs65.3
UNKNOWN125100Substation-Adjacent230 kV300 MW3.0 yrs65.0
HOPE SUPPLY, INC. (NOT AVAILABLE)Manufacturing——3.0 yrs56.2
PYRAMID PAPER PRODUCTS (ALL OTHER CONVERTED PAPER PRODUCT MANUFACTURING)Manufacturing——3.0 yrs56.2
INDIANA CUSTOM MACHINE & TOOL (MACHINE SHOPS)Manufacturing——3.0 yrs56.2
EMCON TECHNOLOGIES, LLC (GASOLINE ENGINE AND ENGINE PARTS MANUFACTURING)Manufacturing——3.0 yrs56.2

Greenfield (UNKNOWN124912 - COLUMBUS (345K): common questions

What is the DC Readiness score of Greenfield (UNKNOWN124912 - COLUMBUS (345K)?

Greenfield (UNKNOWN124912 - COLUMBUS (345K) scores 54.6/100 on the GridCensus DC Readiness scale, rated fair. It ranks 91st of 109 scored sites in BARTHOLOMEW. The BARTHOLOMEW average is 55.7 and the Indiana average is 54.0.

What is the nearest substation to Greenfield (UNKNOWN124912 - COLUMBUS (345K)?

The nearest mapped substation is UNKNOWN124912, at 138 kV. GridCensus catalogs 100 MW of candidate capacity for the site.

Which electric utility serves Greenfield (UNKNOWN124912 - COLUMBUS (345K)?

DUKE ENERGY INDIANA, LLC (investor owned) holds the retail service territory that contains the site; its holding company is DUKE ENERGY CORP.

What grid region is Greenfield (UNKNOWN124912 - COLUMBUS (345K) in?

Greenfield (UNKNOWN124912 - COLUMBUS (345K) is in the MISO region. Projects interconnecting there have averaged a 3.0-year wait from queue request to operation.

How far is Greenfield (UNKNOWN124912 - COLUMBUS (345K) from an internet exchange?

The nearest internet exchange facility is DartPoints Columbus, IN - CLU1, about 7 miles away; 9 fiber providers report service at the location.

Related pages

About this data

Source: GridCensus composite of HIFLD transmission and substation data, EIA, FEMA National Risk Index, FCC broadband data, PeeringDB and ISO interconnection queues, as published October 10, 2026 — GridCensus refreshes it monthly. See the methodology for how records are matched, cleaned and scored.

Cite as: GridCensus, “Greenfield (UNKNOWN124912 - COLUMBUS (345K), BARTHOLOMEW, IN”, https://gridcensus.com/datacenter-sites/indiana/bartholomew/greenfield-unknown124912-columbus-345k-9f7bd674 (data as of October 10, 2026).

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

Every site and score for Greenfield (UNKNOWN124912 - COLUMBUS (345K), BARTHOLOMEW is free to browse. Pro adds Watchtower on 25 sites, alerts when new candidate sites, datacenters or interconnection-queue requests appear in your markets, score and capacity history, and CSV export. Enterprise adds team seats, weekly data files for all 147,272 sites, the REST API and an MCP server for AI tools.