OZ Pulaski

Greenfield

Pulaski County, Illinois · PJM

DC Readiness
55.3
Good / 100

OZ Pulaski is a greenfield datacenter candidate site in Pulaski County, Illinois, interconnecting through PJM. It screens at 55.3/100 DC Readiness and a 4.6 yrs average interconnection-queue wait.

Power & interconnection

LMP zonePJM_COMED
Wholesale LMP$33.95/MWh
Utility commercial rate0.09¢/kWh
UtilitySOUTHERN ILLINOIS ELEC COOPnot available

Speed to power

Interconnection outlookFavorable
≈ 2.9 yrs typical interconnection wait

Shorter queues and healthier completion here — a faster path to energization than the national norm.

ISO / RTO regionPJM
Queue depth393
Avg queue wait4.6 yrs
Recent queue wait2.9 yrs
Completion rate21%
Withdrawal rate79%

Connectivity

Nearest IXPQuad State Internet METRO1 Colocation
IXP distance25.8 mi
Fiber providers2
Fiber coverage14.4%
Nearest cloud providerAzure
Nearest cloud regionnorthcentralus
Cloud region distance332.3 mi

Site characteristics

Site typeGreenfield
Land contactPulaski County Assessor
Land owner typeprivate
Buildability65.0/100
Land cover (NLCD)Cultivated Crops

Risk & environment

Environmental constraintNone (0/100)
Flood zoneZone X
Water stress (WRI)0.60
Wetlands (NWI)Clear
Critical habitatClear
Superfund nearbyClear
Hazard sub-score65/100
Construction cost index112.1 (avg 100)

Location context

Nearest datacenterQuad State Internet METRO1 Colocation
DC distance25.8 mi
Nearest rail2.1 mi
Nearest gas pipeline13.0 mi
Nearest fiber route251.9 mi
County hazard (FEMA NRI)Relatively High (35)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity8.67¢/kWh
Industrial electricity3.10¢/kWh
Cooling degree days1,100
Heating degree days5,600
Land price / acre$5,494

Regulatory climate

Restrictivestate posture · as of 2026-08

New-DC state tax exemptions suspended for 2 years (from Jul 2026).

DC tax incentiveNo / suspended

Incentive detail: Enterprise Zone sales tax exemption; High Impact Business designation for $12M+ DC investments.

Site location

◆ Loading map…
≥ 7560–7540–60≤ 40
This site + 7 nearby

Get alerts

Track OZ Pulaski

Get an email when its DC-readiness score, available capacity, or interconnection-queue status changes.

No spam. Just the alerts you asked for.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
30
Speed to power20%
47
Fiber connectivity12%
56
Energy cost10%
85
Water risk7%
88
Natural hazard6%
65
Buildability7%
65
Labor market4%
50
DC cluster4%
60
Land / acreage3%
40
Construction cost3%
57
Gas pipeline2%
58
Tax incentive1%
100
Climate / cooling1%
70

Nearby comparable sites

Other scored datacenter candidate sites in Pulaski County, ranked by DC Readiness.

Sites near OZ Pulaski
SiteTypeVoltageCapacityQueue waitScore
Greenfield (JOPPA 345 - KELSO)Greenfield345 kV600 MW3.8 yrs57.7
EC FFE Pulaski CountyGreenfield——4.6 yrs57.0
EC Coal Pulaski CountyGreenfield——4.6 yrs55.2
Greenfield (UNKNOWN122326 - JOPPA STATION)Greenfield161 kV100 MW3.8 yrs52.1
Martin Brothers ContainersIndustrial——3.8 yrs50.3
Mine SiteFormer Mine——3.8 yrs50.2
Mound City National CemeteryFederal Excess——3.8 yrs49.9

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for OZ Pulaski, Pulaski County. Pro and Enterprise plans unlock the full 147,272-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.