Greenfield (UNKNOWN122326 - JOPPA STATION) is a greenfield datacenter candidate site in Pulaski County, Illinois, interconnecting through PJM. It screens at 52.1/100 DC Readiness with a catalogued 100 MW of candidate capacity and a 3.8 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationUNKNOWN122326
Substation voltage161 kV
Available capacity100 MW
UtilitySOUTHERN ILLINOIS ELEC COOPnot available

Speed to power

Interconnection outlookModerate
≈ 3.8 yrs typical interconnection wait

Middle-of-the-pack interconnection conditions for this grid.

ISO / RTO regionPJM
Queue depth393
Avg queue wait3.8 yrs

Connectivity

Nearest IXPQuad State Internet METRO1 Colocation
IXP distance13.6 mi
Fiber providers2
Fiber coverage14.4%

Site characteristics

Site typeGreenfield

Risk & environment

Environmental constraintNone (0/100)
Water stress (WRI)Low
Wetlands (NWI)—
Critical habitat—
Superfund nearby—
Hazard sub-score65/100

Location context

Nearest datacenterQuad State Internet METRO1 Colocation
DC distance13.6 mi
County hazard (FEMA NRI)Relatively High (35)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity8.67¢/kWh
Industrial electricity3.10¢/kWh
Cooling degree days1,100
Heating degree days5,600
Land price / acre$5,494

Regulatory climate

Restrictivestate posture · as of 2026-08

New-DC state tax exemptions suspended for 2 years (from Jul 2026).

DC tax incentiveNo / suspended

Incentive detail: Enterprise Zone sales tax exemption; High Impact Business designation for $12M+ DC investments.

Site location

◆ Loading map…
≥ 7560–7540–60≤ 40
This site + 7 nearby

Get alerts

Track Greenfield (UNKNOWN122326 - JOPPA STATION)

Get an email when its DC-readiness score, available capacity, or interconnection-queue status changes.

No spam. Just the alerts you asked for.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
32
Speed to power20%
49
Fiber connectivity12%
63
Energy cost10%
50
Water risk7%
88
Natural hazard6%
65
Buildability7%
50
Labor market4%
50
DC cluster4%
80
Land / acreage3%
40
Construction cost3%
50
Gas pipeline2%
10
Tax incentive1%
100
Climate / cooling1%
70

Nearby comparable sites

Other scored datacenter candidate sites in Pulaski County, ranked by DC Readiness.

Sites near Greenfield (UNKNOWN122326 - JOPPA STATION)
SiteTypeVoltageCapacityQueue waitScore
Greenfield (JOPPA 345 - KELSO)Greenfield345 kV600 MW3.8 yrs57.7
EC FFE Pulaski CountyGreenfield——4.6 yrs57.0
OZ PulaskiGreenfield——4.6 yrs55.3
EC Coal Pulaski CountyGreenfield——4.6 yrs55.2
Martin Brothers ContainersIndustrial——3.8 yrs50.3
Mine SiteFormer Mine——3.8 yrs50.2
Mound City National CemeteryFederal Excess——3.8 yrs49.9

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for Greenfield (UNKNOWN122326 - JOPPA STATION), Pulaski County. Pro and Enterprise plans unlock the full 147,272-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.