EC Near Cudjoe

Greenfield

Monroe County, Florida · SERC

DC Readiness
47.1
Fair / 100

EC Near Cudjoe is a greenfield datacenter candidate site in Monroe County, Florida, interconnecting through SERC. It screens at 47.1/100 DC Readiness and a 3.6 yrs average interconnection-queue wait.

Power & interconnection

Utility commercial rate0.13¢/kWh

Speed to power

ISO / RTO regionSERC
Queue depth1
Avg queue wait3.6 yrs
Recent queue wait3.3 yrs
Completion rate26%
Withdrawal rate74%

Connectivity

Nearest IXPSKYLINK DATA CENTERS
IXP distance110.6 mi
Fiber providers9
Fiber coverage50.0%
Nearest cloud providerGCP
Nearest cloud regionus-east1
Cloud region distance602.9 mi

Site characteristics

Site typeGreenfield
Parcel ownerFLORIDA POWER & LIGHT CO
Land owner typeprivate
Buildability5.0/100
Land cover (NLCD)Water
Former usenear retired oil plant (10km)

Risk & environment

Flood zoneZone X
Water stress (WRI)1.20
Wetlands (NWI)Present
Critical habitatClear
Superfund nearbyClear
Hazard sub-score35/100
Construction cost index86.5 (avg 100)

Location context

Nearest datacenterNocRoom Miami IT Services
DC distance103.6 mi
Nearest rail3.2 mi
Nearest gas pipeline96.6 mi
Nearest fiber route197.7 mi
County hazard (FEMA NRI)Very High (55)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity12.97¢/kWh
Industrial electricity11.69¢/kWh
Cooling degree days3,500
Heating degree days700
Land price / acre$8,966

Incentive detail: Sales tax exemption on manufacturing machinery including servers; no state income tax.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
30
Speed to power15%
75
Fiber connectivity12%
29
Energy cost10%
89
Water risk8%
75
Natural hazard8%
35
Buildability7%
5
Labor market4%
50
DC cluster4%
20
Land / acreage3%
40
Construction cost3%
78
Gas pipeline2%
0
Tax incentive2%
100
Climate / cooling2%
0

Nearby comparable sites

Other scored datacenter candidate sites in Monroe County, ranked by DC Readiness.

Sites near EC Near Cudjoe
SiteTypeVoltageCapacityQueue waitScore
MARATHONSubstation-Adjacent138 kV100 MW3.6 yrs57.9
KENNEDY DRIVESubstation-Adjacent138 kV100 MW3.6 yrs57.5
UNKNOWN108501Substation-Adjacent138 kV100 MW3.6 yrs57.3
MARATHON GENERATING PLANTSubstation-Adjacent138 kV100 MW3.6 yrs56.2
STOCK ISLANDSubstation-Adjacent138 kV100 MW3.6 yrs56.1
UNKNOWN150796Substation-Adjacent138 kV100 MW3.6 yrs55.7
Marathon Generating PlantBrownfield14 MW54.9
UNKNOWN120079Substation-Adjacent138 kV100 MW3.6 yrs54.8

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for EC Near Cudjoe, Monroe County. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.