EC Near Rifle Generating Station

Greenfield

Garfield County, Colorado · WECC

DC Readiness
52.8
Fair / 100

EC Near Rifle Generating Station is a greenfield datacenter candidate site in Garfield County, Colorado, interconnecting through WECC. It screens at 52.8/100 DC Readiness and a 1.7 yrs average interconnection-queue wait.

Power & interconnection

Utility commercial rate0.11¢/kWh

Speed to power

ISO / RTO regionWECC
Queue depth74
Avg queue wait1.7 yrs
Recent queue wait1.0 yrs
Completion rate17%
Withdrawal rate84%

Connectivity

Nearest IXPSTRATA Vernal Data Center
IXP distance112.7 mi
Fiber providers6
Fiber coverage42.9%
Nearest cloud providerGCP
Nearest cloud regionus-west3
Cloud region distance233.1 mi

Site characteristics

Site typeGreenfield
Parcel ownerRifle Mixed Ventures, Llc
Parcel APN217721200400
Land owner typeprivate
Buildability65.0/100
Land cover (NLCD)Cultivated Crops
Former usenear retired gas plant (5km)

Risk & environment

Flood zoneZone X
Water stress (WRI)3.20
Wetlands (NWI)Clear
Critical habitatClear
Superfund nearbyClear
Hazard sub-score75/100
Construction cost index102.2 (avg 100)

Location context

Nearest datacenterStrata Networks
DC distance112.7 mi
Nearest rail0.8 mi
Nearest gas pipeline0.6 mi
Nearest fiber route114.6 mi
County hazard (FEMA NRI)Relatively Moderate (25)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity11.39¢/kWh
Industrial electricity9.05¢/kWh
Cooling degree days700
Heating degree days6,200
Land price / acre$3,654

Incentive detail: Enterprise Zone sales tax exemptions; broadband equipment tax credit.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
30
Speed to power15%
33
Fiber connectivity12%
62
Energy cost10%
89
Water risk8%
36
Natural hazard8%
75
Buildability7%
65
Labor market4%
50
DC cluster4%
20
Land / acreage3%
50
Construction cost3%
65
Gas pipeline2%
98
Tax incentive2%
100
Climate / cooling2%
90

Nearby comparable sites

Other scored datacenter candidate sites in Garfield County, ranked by DC Readiness.

Sites near EC Near Rifle Generating Station
SiteTypeVoltageCapacityQueue waitScore
UNKNOWN203894Substation-Adjacent230 kV300 MW1.7 yrs66.7
TAP203975Substation-Adjacent345 kV600 MW1.7 yrs64.4
RIFLE UTESubstation-Adjacent345 kV600 MW1.7 yrs64.0
STARKEY GULCHSubstation-Adjacent230 kV300 MW1.7 yrs64.0
PARACHUTESubstation-Adjacent230 kV300 MW1.7 yrs62.9
MIDDLE FORKSubstation-Adjacent230 kV300 MW1.7 yrs62.5
WHEELERSubstation-Adjacent230 kV300 MW1.7 yrs61.9
Greenfield (CRAIG - TAP203975)Greenfield345 kV600 MW1.7 yrs59.7

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for EC Near Rifle Generating Station, Garfield County. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.