EC Near Rifle Generating Station

Greenfield

Garfield County, Colorado · WECC

DC Readiness
54.0
Fair / 100

EC Near Rifle Generating Station is a greenfield datacenter candidate site in Garfield County, Colorado, interconnecting through WECC. It screens at 54.0/100 DC Readiness and a 1.7 yrs average interconnection-queue wait.

Power & interconnection

Utility commercial rate0.11¢/kWh
UtilityPUBLIC SERVICE CO OF COLORADOinvestor ownedmoderate to large load · terms ≥ 100 MW

Speed to power

Interconnection outlookFavorable
≈ 1.0 yrs typical interconnection wait

Shorter queues and healthier completion here — a faster path to energization than the national norm.

ISO / RTO regionWECC
Queue depth34
Avg queue wait1.7 yrs
Recent queue wait1.0 yrs
Completion rate17%
Withdrawal rate84%

Connectivity

Nearest IXPSTRATA Vernal Data Center
IXP distance111.8 mi
Fiber providers5
Fiber coverage17.0%
Nearest cloud providerGCP
Nearest cloud regionus-west3
Cloud region distance233.6 mi

Site characteristics

Site typeGreenfield
Land contactGarfield County Assessor
Land owner typeprivate
Buildability50.0/100
Former usenear retired gas plant (10km)

Risk & environment

Environmental constraintNone (0/100)
Flood zoneZone X
Water stress (WRI)3.20
Wetlands (NWI)Clear
Critical habitatClear
Superfund nearbyClear
Hazard sub-score75/100
Construction cost index102.2 (avg 100)

Location context

Nearest datacenterStrata Networks
DC distance111.8 mi
Nearest rail5.2 mi
Nearest gas pipeline4.3 mi
Nearest fiber route120.6 mi
County hazard (FEMA NRI)Relatively Moderate (25)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity11.39¢/kWh
Industrial electricity9.05¢/kWh
Cooling degree days700
Heating degree days6,200
Land price / acre$3,654

Regulatory climate

Moderatestate posture · as of 2026-08

No notable statewide DC restriction on record; confirm local zoning and utility tariffs.

DC tax incentiveNo / suspended

Incentive detail: Enterprise Zone sales tax exemptions; broadband equipment tax credit.

Site location

◆ Loading map…
≥ 7560–7540–60≤ 40
This site + 8 nearby

Get alerts

Track EC Near Rifle Generating Station

Get an email when its DC-readiness score, available capacity, or interconnection-queue status changes.

No spam. Just the alerts you asked for.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
30
Speed to power20%
51
Fiber connectivity12%
52
Energy cost10%
89
Water risk7%
49
Natural hazard6%
75
Buildability7%
50
Labor market4%
50
DC cluster4%
20
Land / acreage3%
52
Construction cost3%
65
Gas pipeline2%
86
Tax incentive1%
100
Climate / cooling1%
90

Nearby comparable sites

Other scored datacenter candidate sites in Garfield County, ranked by DC Readiness.

Sites near EC Near Rifle Generating Station
SiteTypeVoltageCapacityQueue waitScore
RIFLE UTESubstation-Adjacent345 kV600 MW6.9 yrs58.4
TAP203975Substation-Adjacent345 kV600 MW6.9 yrs58.3
UNKNOWN203894Substation-Adjacent230 kV300 MW6.9 yrs57.4
New Rifle MillBrownfield138 kV2 MW6.9 yrs57.1
EC Near Rifle Generating StationGreenfield——1.7 yrs56.8
WHEELERSubstation-Adjacent230 kV300 MW6.9 yrs56.6
PARACHUTESubstation-Adjacent230 kV300 MW6.9 yrs56.6
STARKEY GULCHSubstation-Adjacent230 kV300 MW6.9 yrs56.5

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

Every site and score for EC Near Rifle Generating Station, Garfield County is free to browse. Pro adds Watchtower on 25 sites, alerts when new candidate sites, datacenters or interconnection-queue requests appear in your markets, score and capacity history, and CSV export. Enterprise adds team seats, weekly data files for all 147,272 sites, the REST API and an MCP server for AI tools.