El Paso County, Colorado · WECC

DC Readiness
64.0
Good / 100

MIDWAY is a substation-adjacent datacenter candidate site in El Paso County, Colorado, interconnecting through WECC. It screens at 64.0/100 DC Readiness with a catalogued 600 MW of candidate capacity and a 6.9 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationMIDWAY
Substation distance0.0 mi
Substation voltage345 kV
Available capacity600 MW
UtilityMOUNTAIN VIEW ELEC ASSN, INCcooperativemoderate to large load · state default

Speed to power

Interconnection outlookConstrained
≈ 6.9 yrs typical interconnection wait

Deep queue and long historical waits — plan for a multi-year interconnection timeline and engage the utility early.

ISO / RTO regionWECC
Queue depth34
Avg queue wait6.9 yrs

Connectivity

Nearest IXPT5@Colorado Springs
IXP distance16.4 mi
Fiber providers15
Fiber coverage64.2%

Site characteristics

Risk & environment

Environmental constraintNone (0/100)
Water stress (WRI)High
Wetlands (NWI)—
Critical habitat—
Superfund nearby—
Hazard sub-score75/100

Location context

Nearest datacenterT5@Colorado Springs
DC distance16.4 mi
County hazard (FEMA NRI)Relatively Moderate (25)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity11.55¢/kWh
Industrial electricity9.26¢/kWh
Cooling degree days700
Heating degree days6,200
Land price / acre$2,688

Regulatory climate

Moderatestate posture · as of 2026-08

No notable statewide DC restriction on record; confirm local zoning and utility tariffs.

DC tax incentiveNo / suspended

Incentive detail: Enterprise Zone sales tax exemptions; broadband equipment tax credit.

Site location

◆ Loading map…
≥ 7560–7540–60≤ 40
This site + 8 nearby

Get alerts

Track MIDWAY

Get an email when its DC-readiness score, available capacity, or interconnection-queue status changes.

No spam. Just the alerts you asked for.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
87
Speed to power20%
56
Fiber connectivity12%
79
Energy cost10%
50
Water risk7%
36
Natural hazard6%
75
Buildability7%
60
Labor market4%
50
DC cluster4%
60
Land / acreage3%
52
Construction cost3%
50
Gas pipeline2%
10
Tax incentive1%
100
Climate / cooling1%
90

Nearby comparable sites

Other scored datacenter candidate sites in El Paso County, ranked by DC Readiness.

Sites near MIDWAY
SiteTypeVoltageCapacityQueue waitScore
UNKNOWN202739Substation-Adjacent230 kV300 MW6.9 yrs65.2
OZ El PasoGreenfield——1.7 yrs65.0
OZ El PasoGreenfield——1.7 yrs64.7
EC Near South Plant (CO)Greenfield——1.7 yrs64.4
COTTONWOODSubstation-Adjacent230 kV300 MW6.9 yrs64.4
EC Coal El Paso CountyGreenfield——1.7 yrs63.7
TAP209761Substation-Adjacent230 kV300 MW6.9 yrs63.6
UNKNOWN201277Substation-Adjacent230 kV300 MW6.9 yrs63.5

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for MIDWAY, El Paso County. Pro and Enterprise plans unlock the full 147,272-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.