SC 1 Data Center, Phase 2

Brownfield

Santa Clara County, California · CAISO

DC Readiness
50.0
Fair / 100

SC 1 Data Center, Phase 2 is a brownfield datacenter candidate site in Santa Clara County, California, interconnecting through CAISO. It screens at 50.0/100 DC Readiness with a catalogued 2 MW of candidate capacity and a 5.7 yrs average interconnection-queue wait.

Power & interconnection

Substation distance1.1 mi
Substation voltage115 kV
Available capacity2 MW
LMP zoneCAISO_NP15
Wholesale LMP$16.53/MWh
Utility commercial rate0.28¢/kWh

Speed to power

ISO / RTO regionCAISO
Queue depth311
Avg queue wait5.7 yrs
Recent queue wait3.0 yrs
Completion rate11%
Withdrawal rate89%

Connectivity

Nearest IXPDigital Realty SJC (2220 De La Cruz Blvd)
IXP distance0.0 mi
Fiber providers20
Fiber coverage45.5%
Nearest cloud providerAWS
Nearest cloud regionus-west-1
Cloud region distance3.5 mi

Site characteristics

Site typeBrownfield
Parcel ownerXeres Ventures LLC
Land owner typeprivate
Buildability100.0/100
Land cover (NLCD)Developed, High Intensity
Former useoil
Existing capacity2 MW
Retirement date2020-04-01

Risk & environment

Flood zoneZone X
Water stress (WRI)3.80
Wetlands (NWI)Clear
Critical habitatClear
Superfund nearbyPresent
Superfund siteAKINS COLLISION CTR
Hazard sub-score42/100
Construction cost index147.6 (avg 100)

Location context

Nearest datacenterDigital Realty Silicon Valley SC1
DC distance0.0 mi
Nearest rail0.2 mi
Nearest gas pipeline2.2 mi
Nearest fiber route170.1 mi
County hazard (FEMA NRI)Relatively High (48)
DC tax incentiveNo
Commercial electricity28.22¢/kWh
Industrial electricity21.85¢/kWh
Cooling degree days1,000
Heating degree days2,500
Land price / acre$13,303

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
37
Speed to power15%
38
Fiber connectivity12%
43
Energy cost10%
52
Water risk8%
53
Natural hazard8%
42
Buildability7%
100
Labor market4%
50
DC cluster4%
100
Land / acreage3%
57
Construction cost3%
27
Gas pipeline2%
93
Tax incentive2%
0
Climate / cooling2%
75

Nearby comparable sites

Other scored datacenter candidate sites in Santa Clara County, ranked by DC Readiness.

Sites near SC 1 Data Center, Phase 2
SiteTypeVoltageCapacityQueue waitScore
METCALF 1Substation-Adjacent500 kV1,000 MW5.7 yrs65.2
SARATOGASubstation-Adjacent230 kV300 MW5.7 yrs61.4
HICKSSubstation-Adjacent230 kV300 MW5.7 yrs61.2
COYOTESubstation-Adjacent230 kV300 MW5.7 yrs61.0
Greenfield (MOSS LANDING - METCALF 1)Greenfield500 kV1,000 MW5.7 yrs59.4
STONESubstation-Adjacent115 kV100 MW5.7 yrs58.9
Gish ApartmentsBrownfield58.9
VASONASubstation-Adjacent230 kV300 MW5.7 yrs58.7

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.