EC Near Mountainview Generating Station
GreenfieldSan Bernardino County, California · CAISO
EC Near Mountainview Generating Station is a greenfield datacenter candidate site in San Bernardino County, California, interconnecting through CAISO. It screens at 49.0/100 DC Readiness and a 5.7 yrs average interconnection-queue wait.
Power & interconnection
Speed to power
Middle-of-the-pack interconnection conditions for this grid.
Connectivity
Site characteristics
Risk & environment
Location context
Regulatory climate
No notable statewide DC restriction on record; confirm local zoning and utility tariffs.
Site location
Get alerts
Track EC Near Mountainview Generating Station
Get an email when its DC-readiness score, available capacity, or interconnection-queue status changes.
Full DC Readiness breakdown
All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.
Nearby comparable sites
Other scored datacenter candidate sites in San Bernardino County, ranked by DC Readiness.
| Site | Type | Voltage | Capacity | Queue wait | Score |
|---|---|---|---|---|---|
| OZ San Bernardino | Greenfield | — | — | 5.7 yrs | 52.1 |
| Newmark Ground Water Contamination (Hallmark Industrial Park) | Brownfield | 33 kV | 2 MW | 8.2 yrs | 51.6 |
| OZ San Bernardino | Greenfield | — | — | 5.7 yrs | 50.6 |
| CIMA | Substation-Adjacent | 230 kV | 300 MW | 8.2 yrs | 50.5 |
| GOLDHILL | Substation-Adjacent | 230 kV | 300 MW | 8.2 yrs | 50.5 |
| EC Coal San Bernardino County | Greenfield | — | — | 5.7 yrs | 50.5 |
| EC Near Energy Center | Greenfield | — | — | 5.7 yrs | 50.4 |
| OZ San Bernardino | Greenfield | — | — | 5.7 yrs | 50.3 |
Dataset updated . Screening estimates derived from public data sources.
Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.
Go deeper than the public screen
Every site and score for EC Near Mountainview Generating Station, San Bernardino County is free to browse. Pro adds Watchtower on 25 sites, alerts when new candidate sites, datacenters or interconnection-queue requests appear in your markets, score and capacity history, and CSV export. Enterprise adds team seats, weekly data files for all 147,272 sites, the REST API and an MCP server for AI tools.