VA Palo Alto HCS-VAMC Palo Alto, CA DIv. is a federal excess datacenter candidate site in Monterey, California, interconnecting through CAISO. It screens at 40.7/100 DC Readiness.
Power & interconnection
Connectivity
Risk & environment
Location context
Full DC Readiness breakdown
All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.
Nearby comparable sites
Other scored datacenter candidate sites in Monterey, ranked by DC Readiness.
| Site | Type | Voltage | Capacity | Queue wait | Score |
|---|---|---|---|---|---|
| COBURN | Substation-Adjacent | 230 kV | 300 MW | 5.7 yrs | 54.9 |
| Greenfield (PANOCHE - COBURN) | Greenfield | 230 kV | 300 MW | 5.7 yrs | 52.3 |
| Greenfield (COBURN - MOSS LANDING) | Greenfield | 230 kV | 300 MW | 5.7 yrs | 50.9 |
| EC Near Dynegy Moss Landing Power Plant Hybrid | Greenfield | — | — | 5.7 yrs | 49.1 |
| Greenfield (COBURN - MOSS LANDING) | Greenfield | 230 kV | 300 MW | 5.7 yrs | 47.8 |
| EC Near Dynegy Moss Landing Power Plant Hybrid | Greenfield | — | — | 5.7 yrs | 46.8 |
| Greenfield (PANOCHE - COBURN) | Greenfield | 230 kV | 300 MW | 5.7 yrs | 46.7 |
| EC Near Dynegy Moss Landing Power Plant Hybrid | Greenfield | — | — | 5.7 yrs | 46.4 |
Dataset updated . Screening estimates derived from public data sources.
Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.