Skip to content
Gridcensus

Nu Way Laundry-Mat

Industrial

Phillips, Arkansas · MISO

DC Readiness
47.1
Fair / 100

At a glance

Nu Way Laundry-Mat is an industrial datacenter candidate site in Phillips, Arkansas, scoring 47.1/100 DC Readiness — 22nd of 34 scored sites in the county. It sits in the MISO grid region and the ENTERGY ARKANSAS LLC service territory, where interconnection has averaged 4.3 years from request to operation.

Power & interconnection

UtilityENTERGY ARKANSAS LLCinvestor ownedfavorable to large load · terms ≥ 50 MW

Speed to power

Interconnection outlookModerate
≈ 4.9 yrs typical interconnection wait

Middle-of-the-pack interconnection conditions for this grid.

ISO / RTO regionMISO
Queue depth136
Avg queue wait4.3 yrs
Recent queue wait4.9 yrs
Completion rate18%
Withdrawal rate82%

Connectivity

Nearest IXPARE-ON Forrest City
IXP distance37.0 mi
Fiber providers2
Fiber coverage7.7%

Site characteristics

Site typeIndustrial

Risk & environment

Environmental constraintNone (0/100)
Water stress (WRI)Low
Wetlands (NWI)—
Critical habitat—
Superfund nearby—
Hazard sub-score62/100

Location context

Nearest datacenterARE-ON Forrest City
DC distance37.0 mi
County hazard (FEMA NRI)Relatively High (38)
DC tax incentiveNo
Commercial electricity10.41¢/kWh
Industrial electricity11.54¢/kWh
Cooling degree days1,900
Heating degree days3,400
Land price / acre$3,345

Regulatory climate

Moderatestate posture · as of 2026-08

No notable statewide DC restriction on record; confirm local zoning and utility tariffs.

DC tax incentiveNo / suspended

Site location

◆ Loading map…
≥ 7560–7540–60≤ 40
This site + 8 nearby

Get alerts

Track Nu Way Laundry-Mat

Get an email when its DC-readiness score, available capacity, or interconnection-queue status changes.

No spam. Just the alerts you asked for.

How does Nu Way Laundry-Mat compare with other sites in Phillips?

Nu Way Laundry-Mat ranks 22nd of 34 scored candidate sites in Phillips. Its 47.1/100 is roughly in line with the county average of 51.3. It is about 12% below the Arkansas average of 53.6 and about 11% below the national average of 53.2.

Against the Arkansas average, its strongest sub-score is natural hazard (62 vs 61) and its weakest is fiber connectivity (51 vs 70). Power and speed to power each carry 20% of the composite score, fiber 12%, water 7% and hazard 6%.

How close is Nu Way Laundry-Mat to power, fiber and other datacenters?

The nearest located transmission bottleneck is Horn_Lake_Freeport_161kV_flo_Freeport_500_161kV_ (MISO), 44 miles away. For connectivity, the nearest internet exchange facility is ARE-ON Forrest City at 37 miles. 2 fiber providers report service at the location in FCC broadband data. The closest operating datacenter on record is ARE-ON Forrest City, 37 miles away.

What are the flood, water and hazard risks at Nu Way Laundry-Mat?

At the county level, FEMA's National Risk Index rates Phillips "Relatively High".

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
30
Speed to power20%
49
Fiber connectivity12%
51
Energy cost10%
50
Water risk7%
84
Natural hazard6%
62
Buildability7%
50
Labor market4%
50
DC cluster4%
40
Land / acreage3%
49
Construction cost3%
50
Gas pipeline2%
10
Tax incentive1%
0
Climate / cooling1%
30

Nearby comparable sites

Other scored datacenter candidate sites in Phillips, ranked by DC Readiness.

Sites near Nu Way Laundry-Mat
SiteTypeVoltageCapacityQueue waitScore
RITCHIE STATIONSubstation-Adjacent230 kV300 MW4.3 yrs61.3
TAP149969Substation-Adjacent230 kV300 MW4.3 yrs56.7
TAP149970Substation-Adjacent230 kV300 MW4.3 yrs56.7
EC Near Robert E RitchieGreenfield——4.3 yrs55.3
EC Near Robert E RitchieGreenfield——4.3 yrs54.5
EC Near Robert E RitchieGreenfield——4.3 yrs54.4
EC Near Robert E RitchieGreenfield——4.3 yrs54.4
EC Near Robert E RitchieGreenfield——4.3 yrs54.0

Nu Way Laundry-Mat: common questions

What is the DC Readiness score of Nu Way Laundry-Mat?

Nu Way Laundry-Mat scores 47.1/100 on the GridCensus DC Readiness scale, rated fair. It ranks 22nd of 34 scored sites in Phillips. The Phillips average is 51.3 and the Arkansas average is 53.6.

Which electric utility serves Nu Way Laundry-Mat?

ENTERGY ARKANSAS LLC (investor owned) holds the retail service territory that contains the site; its holding company is ENTERGY CORP.

What grid region is Nu Way Laundry-Mat in?

Nu Way Laundry-Mat is in the MISO region. Projects interconnecting there have averaged a 4.3-year wait from queue request to operation.

How far is Nu Way Laundry-Mat from an internet exchange?

The nearest internet exchange facility is ARE-ON Forrest City, about 37 miles away; 2 fiber providers report service at the location.

Related pages

About this data

Source: GridCensus composite of HIFLD transmission and substation data, EIA, FEMA National Risk Index, FCC broadband data, PeeringDB and ISO interconnection queues, as published October 10, 2026 — GridCensus refreshes it monthly. See the methodology for how records are matched, cleaned and scored.

Cite as: GridCensus, “Nu Way Laundry-Mat, Phillips, AR”, https://gridcensus.com/datacenter-sites/arkansas/phillips/nu-way-laundry-mat-e6830e9e (data as of October 10, 2026).

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

Every site and score for Nu Way Laundry-Mat, Phillips is free to browse. Pro adds Watchtower on 25 sites, alerts when new candidate sites, datacenters or interconnection-queue requests appear in your markets, score and capacity history, and CSV export. Enterprise adds team seats, weekly data files for all 147,272 sites, the REST API and an MCP server for AI tools.