Skip to content
Gridcensus

Desert Star Solar Plant

Brownfield

Maricopa County, Arizona · WECC

DC Readiness
59.9
Good / 100

Desert Star Solar Plant is a brownfield datacenter candidate site in Maricopa County, Arizona, interconnecting through WECC. It screens at 59.9/100 DC Readiness with a catalogued 10 MW of candidate capacity and a 6.9 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationBUCKEYE
Substation distance2.9 mi
Substation voltage230 kV
Available capacity10 MW
Utility commercial rate0.12¢/kWh

Speed to power

ISO / RTO regionWECC
Queue depth34
Avg queue wait6.9 yrs

Connectivity

Nearest IXPStream Data Centers - Phoenix I
IXP distance16.3 mi
Fiber providers27
Fiber coverage52.6%
Nearest cloud providerAzure
Nearest cloud regionwestus3
Cloud region distance32.8 mi

Site characteristics

Site typeBrownfield
Acreage2,560 ac
Land contactState Environmental Cleanup Program
Land owner typeprivate
Buildability75.0/100
Former uselandfill
Existing capacity10 MW
Cleanup statuscleanup_complete

Risk & environment

Flood zoneZone X
Water stress (WRI)4.20
Wetlands (NWI)Clear
Critical habitatClear
Superfund nearbyClear
Hazard sub-score78/100
Construction cost index103.8 (avg 100)

Location context

Nearest datacenterDatacenter 00938592711
DC distance15.3 mi
Nearest rail4.0 mi
Nearest gas pipeline13.3 mi
County hazard (FEMA NRI)Relatively Low (22)
DC tax incentiveYes (property_tax_reduction)
Commercial electricity12.24¢/kWh
Industrial electricity8.99¢/kWh
Cooling degree days3,400
Heating degree days1,500
Land price / acre$7,203

Incentive detail: Government Property Lease Excise Tax (GPLET) for qualified facilities on government land.

Site location

◆ Loading map…
≥ 7560–7540–60≤ 40
This site + 8 nearby

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
36
Speed to power15%
44
Fiber connectivity12%
74
Energy cost10%
97
Water risk8%
41
Natural hazard8%
78
Buildability7%
75
Labor market4%
50
DC cluster4%
90
Land / acreage3%
76
Construction cost3%
64
Gas pipeline2%
57
Tax incentive2%
100
Climate / cooling2%
0

Nearby comparable sites

Other scored datacenter candidate sites in Maricopa County, ranked by DC Readiness.

Sites near Desert Star Solar Plant
SiteTypeVoltageCapacityQueue waitScore
RUDDSubstation-Adjacent500 kV1,000 MW6.9 yrs64.3
KYRENESubstation-Adjacent500 kV1,000 MW6.9 yrs64.2
PINNACLE PEAK APSSubstation-Adjacent500 kV1,000 MW6.9 yrs63.1
Williams Air Force BaseBrownfield69 kV2 MW6.9 yrs62.2
WARDSubstation-Adjacent230 kV300 MW6.9 yrs61.5
WESTWINGSubstation-Adjacent500 kV1,000 MW6.9 yrs61.4
MORGANSubstation-Adjacent500 kV1,000 MW6.9 yrs61.2
EC Near CrosscutGreenfield5.7 yrs60.9

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for Desert Star Solar Plant, Maricopa County. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.