Duncan Gin

Industrial

Greenlee, Arizona · WECC

DC Readiness
45.7
Fair / 100

Duncan Gin is an industrial datacenter candidate site in Greenlee, Arizona, interconnecting through WECC. It screens at 45.7/100 DC Readiness and a 6.9 yrs average interconnection-queue wait.

Power & interconnection

UtilityMORENCI WATER AND ELECTRICinvestor owned

Speed to power

Interconnection outlookConstrained
≈ 6.9 yrs typical interconnection wait

Deep queue and long historical waits — plan for a multi-year interconnection timeline and engage the utility early.

ISO / RTO regionWECC
Queue depth34
Avg queue wait6.9 yrs

Connectivity

Nearest IXPLogin Tucson
IXP distance114.3 mi
Fiber providers2
Fiber coverage48.6%

Site characteristics

Site typeIndustrial

Risk & environment

Environmental constraintNone (0/100)
Water stress (WRI)Extremely High
Wetlands (NWI)
Critical habitat
Superfund nearby
Hazard sub-score78/100

Location context

Nearest datacenterDirecTV DC
DC distance87.8 mi
County hazard (FEMA NRI)Relatively Low (22)
DC tax incentiveYes (property_tax_reduction)
Commercial electricity11.00¢/kWh
Industrial electricity8.60¢/kWh
Cooling degree days3,400
Heating degree days1,500
Land price / acre$5,515

Regulatory climate

Restrictivestate posture · as of 2026-08

Sales-tax exemption suspended Jul 2026–Jun 2029; water constraints add scrutiny.

DC tax incentiveNo / suspended

Incentive detail: Government Property Lease Excise Tax (GPLET) for qualified facilities on government land.

Site location

◆ Loading map…
≥ 7560–7540–60≤ 40
This site + 8 nearby

Get alerts

Track Duncan Gin

Get an email when its DC-readiness score, available capacity, or interconnection-queue status changes.

No spam. Just the alerts you asked for.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
30
Speed to power20%
57
Fiber connectivity12%
57
Energy cost10%
50
Water risk7%
16
Natural hazard6%
78
Buildability7%
50
Labor market4%
50
DC cluster4%
20
Land / acreage3%
52
Construction cost3%
50
Gas pipeline2%
10
Tax incentive1%
100
Climate / cooling1%
0

Nearby comparable sites

Other scored datacenter candidate sites in Greenlee, ranked by DC Readiness.

Sites near Duncan Gin
SiteTypeVoltageCapacityQueue waitScore
GREENLEESubstation-Adjacent345 kV600 MW6.9 yrs58.2
MORENCISubstation-Adjacent230 kV300 MW6.9 yrs56.6
UNKNOWN309814Substation-Adjacent115 kV100 MW6.9 yrs52.2
OZ GreenleeGreenfield5.7 yrs51.8
EC FFE Greenlee CountyGreenfield5.7 yrs51.2
OZ GreenleeGreenfield5.7 yrs46.3
Mine SiteFormer Mine6.9 yrs46.2
Mine SiteFormer Mine6.9 yrs46.1

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for Duncan Gin, Greenlee. Pro and Enterprise plans unlock the full 147,272-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.