Skip to content
Gridcensus

Procter & Gamble Cincinnati Plant

Brownfield

Cincinnati, Hamilton, Ohio · Procter & Gamble Co

Legacy capacity
13
MW

Procter & Gamble Cincinnati Plant is a natural gas plant in Cincinnati, Hamilton, Ohio, retired 2024-12-01. Retired generation sites are among the most attractive datacenter redevelopment targets: the existing interconnection was sized for roughly 13 MW of generation, so the grid hookup, transmission rights, and often cooling-water access are already in place — collapsing the speed-to-power timeline versus a greenfield build.

Former use & capacity

Former usenatural gas plant
Site typeretired_plant
Existing capacity13 MW
Retirement date2024-12-01
EIA plant ID#50456

Grid hookup & remediation

Nearest substation0.2 mi
Operator address5201 Spring Grove Avenue, Cincinnati, OH, 45217
Why this site is datacenter-attractive: a natural gas plant of this scale leaves behind a high-capacity grid interconnection that a new load can re-use, frequently shaving years off the interconnection queue. Retired-plant sites also tend to be already zoned for heavy industrial use with established road, rail, and water infrastructure.

Nearby datacenter candidate sites

Scored candidate sites near Procter & Gamble Cincinnati Plant, ranked by DC Readiness.

Candidate sites near Procter & Gamble Cincinnati Plant
SiteTypeStateCountyVoltageCapacityQueue waitScore
UNKNOWN113763Substation-AdjacentOHHamilton County345 kV600 MW3.8 yrs70.3
PIERCESubstation-AdjacentOHCampbell County345 kV600 MW3.8 yrs70.2
UNKNOWN113618Substation-AdjacentOHHamilton County345 kV600 MW3.8 yrs69.3
UNKNOWN113672Substation-AdjacentOHHamilton County345 kV600 MW3.8 yrs69.1
PORT UNION SUBSTATIONSubstation-AdjacentOHButler County345 kV600 MW3.8 yrs68.8
MIAMISubstation-AdjacentOHDearborn County345 kV600 MW3.8 yrs68.7
FOSTERSubstation-AdjacentOHWarren County345 kV600 MW3.8 yrs68.7
UNKNOWN124886Substation-AdjacentINDearborn County345 kV600 MW3.8 yrs68.7

Nearby internet exchanges

See all datacenter sites in Ohio

Dataset updated . Screening estimates derived from public data sources.

Brownfield attributes are derived from EIA retired-generator and EPA public data. Existing capacity reflects the retired plant's historical nameplate, not deliverable interconnection for a new load. Confirm reusable interconnection rights, remediation status, and site availability with the utility, ISO, and current owner.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for Procter & Gamble Cincinnati Plant, Cincinnati, Hamilton, Ohio. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.