TAP162974

Substation

Wisconsin

Max voltage
69
kV

At a glance

TAP162974 is a 69 kV electric substation in Wisconsin, recorded in the HIFLD transmission dataset. 3 transmission lines connect to it. The highest-scoring datacenter candidate site within about 25 miles is EC Coal Dubuque County in Dubuque County, with a DC Readiness score of 62/100.

TAP162974 is an electric transmission substation in Wisconsin. It is classified as distribution (69–115 kv) and connects 3 transmission lines. Substation proximity is one of the strongest speed-to-power signals for siting a datacenter — interconnection distance to an energized, high-voltage bus is often the binding constraint on time-to-energization.

Voltage & classification

Max voltage69 kV
Min voltage69 kV
Voltage classDistribution (69–115 kV)
Connected lines3

Ownership

No owner is recorded for the lines that connect here.

Coordinates42.8203, -90.6298

Connected transmission lines

Lines terminating at or passing through this substation, by HIFLD line ID, highest voltage first.

Line IDVoltageOwnerStatusLength
#16055469 kV—IN SERVICE11.1 mi
#16055569 kV—IN SERVICE5.4 mi
#16055669 kV—IN SERVICE6.2 mi

Browse the full transmission-line map →

Nearby datacenter candidate sites

Scored candidate sites within roughly 25 miles of TAP162974, ranked by DC Readiness. Sites this close to an energized substation carry a strong speed-to-power advantage.

Candidate sites near TAP162974 substation
SiteTypeStateCountyVoltageCapacityQueue waitScore
EC Coal Dubuque CountyGreenfieldIADubuque County——4.3 yrs62.2
EC Coal Dubuque CountyGreenfieldIADubuque County——4.3 yrs62.0
NELSON DEWEY SW YDSubstation-AdjacentWIClayton County161 kV100 MW4.3 yrs61.4
EC Near DubuqueGreenfieldIADubuque——4.3 yrs61.2
EC Coal Jo Daviess CountyGreenfieldILJo Daviess County——4.8 yrs60.8
UNKNOWN130699Substation-AdjacentIADubuque County161 kV100 MW4.3 yrs60.4
UNKNOWN136983Substation-AdjacentIADubuque County161 kV100 MW4.3 yrs60.1
UNKNOWN131370Substation-AdjacentIADubuque County161 kV100 MW4.3 yrs59.9

How do candidate sites near TAP162974 score?

The 8 highest-scoring candidate sites within about 25 miles range from 60 to 62 on the 0–100 DC Readiness scale. They fall in Dubuque County, Clayton County, Dubuque, Jo Daviess County. The Wisconsin average across 3,340 scored sites is 55.4. 1,248 of those Wisconsin sites are classed as substation sites (candidate locations generated at an existing substation).

Frequently asked questions

What voltage is TAP162974 substation?

TAP162974 has a maximum voltage of 69 kV. That places it in the 69–114 kV band. The median named US substation in this dataset is 115 kV, so TAP162974 is below the national midpoint.

How many transmission lines connect to TAP162974 substation?

3 transmission lines terminate at or pass through TAP162974 in the HIFLD line data. The connected lines listed here run at 69 kV. Together the listed lines cover about 22.6 miles.

Where is TAP162974 substation located?

TAP162974 is in Wisconsin at 42.8203, -90.6298. The datacenter candidate sites closest to it are in Dubuque County, Clayton County, Dubuque.

Are there datacenter candidate sites near TAP162974 substation?

GridCensus lists at least 8 scored candidate sites within roughly 25 miles of TAP162974. The highest-scoring is EC Coal Dubuque County at 62/100. Across Wisconsin, the average DC Readiness score is 55.4.

More in Wisconsin

About this data

Source: HIFLD Electric Substations and Transmission Lines (U.S. Department of Homeland Security), as published June 29, 2026. See the methodology for how records are matched, cleaned and scored.

Cite as: GridCensus, “TAP162974 substation, Wisconsin”, https://gridcensus.com/substations/wisconsin/tap162974-22a39989 (data as of June 29, 2026).

Dataset updated . Screening estimates derived from public data sources.

Substation attributes are derived from public HIFLD / EIA infrastructure data and may lag real-world upgrades or retirements. Voltage and connected-line counts are screening figures — confirm available capacity and interconnection terms directly with the operating utility and ISO.

Go deeper than the public screen

Every site and score for TAP162974 substation, Wisconsin is free to browse. Pro adds Watchtower on 25 sites, alerts when new candidate sites, datacenters or interconnection-queue requests appear in your markets, score and capacity history, and CSV export. Enterprise adds team seats, weekly data files for all 147,272 sites, the REST API and an MCP server for AI tools.