TARLETT
SubstationWashington · BONNEVILLE POWER ADMINISTRATION
At a glance
TARLETT is an electric transmission substation in Washington, on BONNEVILLE POWER ADMINISTRATION's transmission network. It is classified as sub-transmission (138 kv) and connects 4 transmission lines. Substation proximity is one of the strongest speed-to-power signals for siting a datacenter — interconnection distance to an energized, high-voltage bus is often the binding constraint on time-to-energization.
Voltage & classification
Ownership
Connected transmission lines
Lines terminating at or passing through this substation, by HIFLD line ID, highest voltage first.
| Line ID | Voltage | Owner | Status | Length |
|---|---|---|---|---|
| #208121 | 138 kV | PUD NO 2 OF PACIFIC COUNTY | — | 8.4 mi |
| #207342 | 115 kV | BONNEVILLE POWER ADMINISTRATION | — | 0.0 mi |
| #207343 | 115 kV | BONNEVILLE POWER ADMINISTRATION | — | 4.3 mi |
| #212143 | 69 kV | PUD NO 2 OF PACIFIC COUNTY | — | 0.0 mi |
Nearby datacenter candidate sites
Scored candidate sites within roughly 25 miles of TARLETT, ranked by DC Readiness. Sites this close to an energized substation carry a strong speed-to-power advantage.
| Site | Type | State | County | Voltage | Capacity | Queue wait | Score |
|---|---|---|---|---|---|---|---|
| CLATSOP | Substation-Adjacent | OR | Clatsop County | 230 kV | 300 MW | 3.5 yrs | 58.7 |
| OZ Pacific | Greenfield | WA | Pacific | — | — | 3.5 yrs | 56.3 |
| OZ Clatsop | Greenfield | OR | Clatsop | — | — | 3.5 yrs | 55.9 |
| YOUNGS BAY | Substation-Adjacent | OR | Clatsop County | 115 kV | 100 MW | 3.5 yrs | 54.5 |
| FERN HILL | Substation-Adjacent | OR | Clatsop County | 115 kV | 100 MW | 3.5 yrs | 54.4 |
| TAP206961 | Substation-Adjacent | OR | Clatsop County | 115 kV | 100 MW | 3.5 yrs | 54.3 |
| WARRENTON | Substation-Adjacent | OR | Clatsop County | 115 kV | 100 MW | 3.5 yrs | 54.2 |
| SEASIDE | Substation-Adjacent | OR | Clatsop County | 115 kV | 100 MW | 3.5 yrs | 54.2 |
How does TARLETT compare with other substations in Washington?
Washington has 2,106 substation records in HIFLD, of which 785 carry a station name; the rest are unnamed tap points, risers and line ends. 515 named substations in the state are in TARLETT's 115–229 kV band (66% of named stations). 137 sit in a higher band. 34 named substations in Washington operate at 345 kV or above. The highest voltage recorded in the state is 500 kV, and the state median is 115 kV.
Who owns the transmission lines at TARLETT?
The 4 connected lines listed above are owned by PUD NO 2 OF PACIFIC COUNTY, BONNEVILLE POWER ADMINISTRATION. Line voltages range from 69 kV to 138 kV. Their combined recorded length is about 12.8 miles.
How do candidate sites near TARLETT score?
The 8 highest-scoring candidate sites within about 25 miles range from 54 to 59 on the 0–100 DC Readiness scale. They fall in Clatsop County, Pacific, Clatsop. The Washington average across 6,019 scored sites is 51.7. 1,343 of those Washington sites are classed as substation sites (candidate locations generated at an existing substation).
Frequently asked questions
What voltage is TARLETT substation?
TARLETT has a maximum voltage of 138 kV and a minimum of 69 kV. That places it in the 115–229 kV band. The median named US substation in this dataset is 115 kV, so TARLETT is above the national midpoint.
How many transmission lines connect to TARLETT substation?
4 transmission lines terminate at or pass through TARLETT in the HIFLD line data. The connected lines listed here run at 138 kV, 115 kV, 69 kV. Together the listed lines cover about 12.8 miles.
Who owns TARLETT substation?
HIFLD does not publish substation owners directly. Most of the transmission lines that end at TARLETT belong to BONNEVILLE POWER ADMINISTRATION, and others to PUD NO 2 OF PACIFIC COUNTY. GridCensus derives this from the line data, so confirm ownership with the utility for anything contractual.
Where is TARLETT substation located?
TARLETT is in Washington at 46.3711, -124.0261. The datacenter candidate sites closest to it are in Clatsop County, Pacific, Clatsop.
Are there datacenter candidate sites near TARLETT substation?
GridCensus lists at least 8 scored candidate sites within roughly 25 miles of TARLETT. The highest-scoring is CLATSOP at 59/100. Across Washington, the average DC Readiness score is 51.7.
Other 138 kV substations in Washington
- MARCH POINT· 10 lines
- COSMOPOLIS· 6 lines
- SNOQUALMIE· 6 lines
- COWLITZ· 5 lines
- STRATFORD· 4 lines
- CEDAR FALLS· 3 lines
- INDUSTRIAL WAY· 3 lines
- MOUNT SI· 3 lines
- All named substations in Washington· 785 stations
- Datacenter candidate sites in Washington· 6,019 sites
- Brownfield and retired plant sites in Washington
- Substations by state
About this data
Source: HIFLD Electric Substations and Transmission Lines (U.S. Department of Homeland Security), as published June 29, 2026. See the methodology for how records are matched, cleaned and scored.
Cite as: GridCensus, “TARLETT substation, Washington”, https://gridcensus.com/substations/washington/tarlett-6aeecf33 (data as of June 29, 2026).
Dataset updated . Screening estimates derived from public data sources.
Substation attributes are derived from public HIFLD / EIA infrastructure data and may lag real-world upgrades or retirements. Voltage and connected-line counts are screening figures — confirm available capacity and interconnection terms directly with the operating utility and ISO.
Go deeper than the public screen
Every site and score for TARLETT substation, Washington is free to browse. Pro adds Watchtower on 25 sites, alerts when new candidate sites, datacenters or interconnection-queue requests appear in your markets, score and capacity history, and CSV export. Enterprise adds team seats, weekly data files for all 147,272 sites, the REST API and an MCP server for AI tools.