TAP169642
SubstationNorth Carolina · DUKE ENERGY PROGRESS - (NC)
At a glance
TAP169642 is an electric transmission substation in North Carolina, on DUKE ENERGY PROGRESS - (NC)'s transmission network. It is classified as unclassified and connects 3 transmission lines. Substation proximity is one of the strongest speed-to-power signals for siting a datacenter — interconnection distance to an energized, high-voltage bus is often the binding constraint on time-to-energization.
Voltage & classification
Ownership
Connected transmission lines
Lines terminating at or passing through this substation, by HIFLD line ID, highest voltage first.
| Line ID | Voltage | Owner | Status | Length |
|---|---|---|---|---|
| #171407 | — | DUKE ENERGY PROGRESS - (NC) | IN SERVICE | 1.7 mi |
| #171408 | — | DUKE ENERGY PROGRESS - (NC) | IN SERVICE | 0.1 mi |
| #171409 | — | DUKE ENERGY PROGRESS - (NC) | IN SERVICE | 1.3 mi |
Nearby datacenter candidate sites
Scored candidate sites within roughly 25 miles of TAP169642, ranked by DC Readiness. Sites this close to an energized substation carry a strong speed-to-power advantage.
| Site | Type | State | County | Voltage | Capacity | Queue wait | Score |
|---|---|---|---|---|---|---|---|
| CUMBERLAND | Substation-Adjacent | NC | Cumberland County | 500 kV | 1,000 MW | 5.3 yrs | 65.8 |
| UNKNOWN114113 | Substation-Adjacent | NC | Cumberland County | 230 kV | 300 MW | 5.3 yrs | 61.8 |
| WOODRUFF STREET | Substation-Adjacent | NC | Cumberland County | 230 kV | 300 MW | 5.3 yrs | 61.8 |
| FAYETTEVILLE | Substation-Adjacent | NC | Cumberland County | 230 kV | 300 MW | 5.3 yrs | 61.8 |
| FAYETTEVILLE EAST | Substation-Adjacent | NC | Cumberland County | 230 kV | 300 MW | 5.3 yrs | 61.8 |
| RAEFORD | Substation-Adjacent | NC | Hoke County | 230 kV | 300 MW | 5.3 yrs | 61.7 |
| UNKNOWN114104 | Substation-Adjacent | NC | Cumberland County | 230 kV | 300 MW | 5.3 yrs | 61.7 |
| TAP147222 | Substation-Adjacent | NC | Hoke County | 230 kV | 300 MW | 5.3 yrs | 61.7 |
Who owns the transmission lines at TAP169642?
The 3 connected lines listed above are owned by DUKE ENERGY PROGRESS - (NC). Their combined recorded length is about 3.1 miles.
How do candidate sites near TAP169642 score?
The 8 highest-scoring candidate sites within about 25 miles range from 62 to 66 on the 0–100 DC Readiness scale. They fall in Cumberland County, Hoke County. The North Carolina average across 2,778 scored sites is 55.1. 1,087 of those North Carolina sites are classed as substation sites (candidate locations generated at an existing substation).
Frequently asked questions
How many transmission lines connect to TAP169642 substation?
3 transmission lines terminate at or pass through TAP169642 in the HIFLD line data. Together the listed lines cover about 3.1 miles.
Who owns TAP169642 substation?
HIFLD does not publish substation owners directly. Most of the transmission lines that end at TAP169642 belong to DUKE ENERGY PROGRESS - (NC). GridCensus derives this from the line data, so confirm ownership with the utility for anything contractual.
Where is TAP169642 substation located?
TAP169642 is in North Carolina at 35.0319, -79.0680. The datacenter candidate sites closest to it are in Cumberland County, Hoke County.
Are there datacenter candidate sites near TAP169642 substation?
GridCensus lists at least 8 scored candidate sites within roughly 25 miles of TAP169642. The highest-scoring is CUMBERLAND at 66/100. Across North Carolina, the average DC Readiness score is 55.1.
More in North Carolina
About this data
Source: HIFLD Electric Substations and Transmission Lines (U.S. Department of Homeland Security), as published June 29, 2026. See the methodology for how records are matched, cleaned and scored.
Cite as: GridCensus, “TAP169642 substation, North Carolina”, https://gridcensus.com/substations/north-carolina/tap169642-6f11a740 (data as of June 29, 2026).
Dataset updated . Screening estimates derived from public data sources.
Substation attributes are derived from public HIFLD / EIA infrastructure data and may lag real-world upgrades or retirements. Voltage and connected-line counts are screening figures — confirm available capacity and interconnection terms directly with the operating utility and ISO.
Go deeper than the public screen
Every site and score for TAP169642 substation, North Carolina is free to browse. Pro adds Watchtower on 25 sites, alerts when new candidate sites, datacenters or interconnection-queue requests appear in your markets, score and capacity history, and CSV export. Enterprise adds team seats, weekly data files for all 147,272 sites, the REST API and an MCP server for AI tools.