At a glance

TAP138439 is a 115 kV electric substation in New York operated by ROCHESTER GAS & ELECTRIC CORP, recorded in the HIFLD transmission dataset. 3 transmission lines connect to it. The highest-scoring datacenter candidate site within about 25 miles is ROCHESTER #80 in Monroe County, with a DC Readiness score of 66/100.

TAP138439 is an electric transmission substation in New York, operated by ROCHESTER GAS & ELECTRIC CORP. It is classified as sub-transmission (115 kv) and connects 3 transmission lines. Substation proximity is one of the strongest speed-to-power signals for siting a datacenter — interconnection distance to an energized, high-voltage bus is often the binding constraint on time-to-energization.

Voltage & classification

Max voltage115 kV
Min voltage115 kV
Voltage classSub-transmission (115 kV)
Connected lines3

Ownership & operation

Coordinates43.0869, -77.4325

Connected transmission lines

Lines terminating at or passing through this substation, by HIFLD line ID, highest voltage first.

Line IDVoltageOwnerStatusLength
#132498115 kVROCHESTER GAS & ELECTRIC CORPIN SERVICE5.5 mi
#134094115 kVROCHESTER GAS & ELECTRIC CORPIN SERVICE1.6 mi
#150780115 kVROCHESTER GAS & ELECTRIC CORPIN SERVICE0.0 mi

Browse the full transmission-line map →

Nearby datacenter candidate sites

Scored candidate sites within roughly 25 miles of TAP138439, ranked by DC Readiness. Sites this close to an energized substation carry a strong speed-to-power advantage.

Candidate sites near TAP138439 substation
SiteTypeStateCountyVoltageCapacityQueue waitScore
ROCHESTER #80Substation-AdjacentNYMonroe County345 kV600 MW4.3 yrs65.6
PANNELLSubstation-AdjacentNYOntario County345 kV600 MW4.3 yrs65.4
City of Canandaigua - Phase IBrownfieldNYOntario—2 MW4.3 yrs63.0
UNKNOWN124706Substation-AdjacentNYMonroe County115 kV100 MW4.3 yrs62.3
UNKNOWN124708Substation-AdjacentNYMonroe County115 kV100 MW4.3 yrs61.8
RED-Rochester, LLCBrownfieldNYMonroe County—89 MW4.3 yrs61.8
OZ MonroeGreenfieldNYMonroe——4.3 yrs61.5
EC Near Rochester 3GreenfieldNYMonroe——4.3 yrs61.3

Who owns the transmission lines at TAP138439?

The 3 connected lines listed above are owned by ROCHESTER GAS & ELECTRIC CORP. Line voltages range from 115 kV to 115 kV. Their combined recorded length is about 7.2 miles.

How do candidate sites near TAP138439 score?

The 8 highest-scoring candidate sites within about 25 miles range from 61 to 66 on the 0–100 DC Readiness scale. They fall in Monroe County, Ontario County, Ontario, Monroe. The New York average across 2,980 scored sites is 54. 844 of those New York sites are classed as substation sites (candidate locations generated at an existing substation).

Frequently asked questions

What voltage is TAP138439 substation?

TAP138439 has a maximum voltage of 115 kV. That places it in the 115–229 kV band. The median named US substation in this dataset is 115 kV, so TAP138439 is at the national midpoint.

How many transmission lines connect to TAP138439 substation?

3 transmission lines terminate at or pass through TAP138439 in the HIFLD line data. The connected lines listed here run at 115 kV. Together the listed lines cover about 7.2 miles.

Who owns TAP138439 substation?

HIFLD lists ROCHESTER GAS & ELECTRIC CORP as the operator of TAP138439.

Where is TAP138439 substation located?

TAP138439 is in New York at 43.0869, -77.4325. The datacenter candidate sites closest to it are in Monroe County, Ontario County, Ontario.

Are there datacenter candidate sites near TAP138439 substation?

GridCensus lists at least 8 scored candidate sites within roughly 25 miles of TAP138439. The highest-scoring is ROCHESTER #80 at 66/100. Across New York, the average DC Readiness score is 54.

More in New York

About this data

Source: HIFLD Electric Substations and Transmission Lines (U.S. Department of Homeland Security), as published June 29, 2026. See the methodology for how records are matched, cleaned and scored.

Cite as: GridCensus, “TAP138439 substation, New York”, https://gridcensus.com/substations/new-york/tap138439-4f53cffb (data as of June 29, 2026).

Dataset updated . Screening estimates derived from public data sources.

Substation attributes are derived from public HIFLD / EIA infrastructure data and may lag real-world upgrades or retirements. Voltage and connected-line counts are screening figures — confirm available capacity and interconnection terms directly with the operating utility and ISO.

Go deeper than the public screen

Every site and score for TAP138439 substation, New York is free to browse. Pro adds Watchtower on 25 sites, alerts when new candidate sites, datacenters or interconnection-queue requests appear in your markets, score and capacity history, and CSV export. Enterprise adds team seats, weekly data files for all 147,272 sites, the REST API and an MCP server for AI tools.