Skip to content
Gridcensus

TAP140629

Substation

Kansas · MIDWEST ENERGY INC

Max voltage
115
kV

At a glance

TAP140629 is a 115 kV electric substation in Kansas on MIDWEST ENERGY INC's transmission network, recorded in the HIFLD transmission dataset. 3 transmission lines connect to it. The highest-scoring datacenter candidate site within about 25 miles is EC Near Colby City of in Thomas, with a DC Readiness score of 58/100.

TAP140629 is an electric transmission substation in Kansas, on MIDWEST ENERGY INC's transmission network. It is classified as sub-transmission (115 kv) and connects 3 transmission lines. Substation proximity is one of the strongest speed-to-power signals for siting a datacenter — interconnection distance to an energized, high-voltage bus is often the binding constraint on time-to-energization.

Voltage & classification

Max voltage115 kV
Min voltage115 kV
Voltage classSub-transmission (115 kV)
Connected lines3

Ownership

Line owner (most lines)MIDWEST ENERGY INC
StateKansas
Coordinates39.8002, -101.3357

Connected transmission lines

Lines terminating at or passing through this substation, by HIFLD line ID, highest voltage first.

Line IDVoltageOwnerStatusLength
#100082115 kVMIDWEST ENERGY INCIN SERVICE3.9 mi
#121870115 kVMIDWEST ENERGY INCIN SERVICE8.8 mi
#143835115 kVMIDWEST ENERGY INCIN SERVICE15.7 mi

Browse the full transmission-line map →

Nearby datacenter candidate sites

Scored candidate sites within roughly 25 miles of TAP140629, ranked by DC Readiness. Sites this close to an energized substation carry a strong speed-to-power advantage.

Candidate sites near TAP140629 substation
SiteTypeStateCountyVoltageCapacityQueue waitScore
EC Near Colby City ofGreenfieldKSThomas——4.3 yrs57.5
EC Near Colby City ofGreenfieldKSThomas——4.3 yrs57.1
EC Near Colby City ofGreenfieldKSThomas——4.3 yrs56.6
UNKNOWN117977Substation-AdjacentKSThomas County115 kV100 MW4.3 yrs55.7
UNKNOWN157314Substation-AdjacentNEDundy County69 kV50 MW4.3 yrs54.8
TAP168056Substation-AdjacentNEDundy County69 kV50 MW4.3 yrs54.7
TAP140629Substation-AdjacentKSRawlins County115 kV100 MW4.3 yrs54.6
UNKNOWN119598Substation-AdjacentKSCheyenne County115 kV100 MW4.3 yrs54.6

Who owns the transmission lines at TAP140629?

The 3 connected lines listed above are owned by MIDWEST ENERGY INC. Line voltages range from 115 kV to 115 kV. Their combined recorded length is about 28.4 miles.

How do candidate sites near TAP140629 score?

The 8 highest-scoring candidate sites within about 25 miles range from 55 to 58 on the 0–100 DC Readiness scale. They fall in Thomas, Thomas County, Dundy County, Rawlins County. The Kansas average across 2,352 scored sites is 53.2. 730 of those Kansas sites are classed as substation sites (candidate locations generated at an existing substation).

Frequently asked questions

What voltage is TAP140629 substation?

TAP140629 has a maximum voltage of 115 kV. That places it in the 115–229 kV band. The median named US substation in this dataset is 115 kV, so TAP140629 is at the national midpoint.

How many transmission lines connect to TAP140629 substation?

3 transmission lines terminate at or pass through TAP140629 in the HIFLD line data. The connected lines listed here run at 115 kV. Together the listed lines cover about 28.4 miles.

Who owns TAP140629 substation?

HIFLD does not publish substation owners directly. Most of the transmission lines that end at TAP140629 belong to MIDWEST ENERGY INC. GridCensus derives this from the line data, so confirm ownership with the utility for anything contractual.

Where is TAP140629 substation located?

TAP140629 is in Kansas at 39.8002, -101.3357. The datacenter candidate sites closest to it are in Thomas, Thomas County, Dundy County.

Are there datacenter candidate sites near TAP140629 substation?

GridCensus lists at least 8 scored candidate sites within roughly 25 miles of TAP140629. The highest-scoring is EC Near Colby City of at 58/100. Across Kansas, the average DC Readiness score is 53.2.

More in Kansas

About this data

Source: HIFLD Electric Substations and Transmission Lines (U.S. Department of Homeland Security), as published June 29, 2026. See the methodology for how records are matched, cleaned and scored.

Cite as: GridCensus, “TAP140629 substation, Kansas”, https://gridcensus.com/substations/kansas/tap140629-0d2873ee (data as of June 29, 2026).

Dataset updated . Screening estimates derived from public data sources.

Substation attributes are derived from public HIFLD / EIA infrastructure data and may lag real-world upgrades or retirements. Voltage and connected-line counts are screening figures — confirm available capacity and interconnection terms directly with the operating utility and ISO.

Go deeper than the public screen

Every site and score for TAP140629 substation, Kansas is free to browse. Pro adds Watchtower on 25 sites, alerts when new candidate sites, datacenters or interconnection-queue requests appear in your markets, score and capacity history, and CSV export. Enterprise adds team seats, weekly data files for all 147,272 sites, the REST API and an MCP server for AI tools.