Skip to content
Gridcensus

Natrona County, Wyoming · WECC

DC Readiness
50.7
Fair / 100

TAP209454 is a substation-adjacent datacenter candidate site in Natrona County, Wyoming, interconnecting through WECC. It screens at 50.7/100 DC Readiness with a catalogued 50 MW of candidate capacity and a 6.9 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationTAP209454
Substation distance0.0 mi
Substation voltage69 kV
Available capacity50 MW

Speed to power

ISO / RTO regionWECC
Queue depth34
Avg queue wait6.9 yrs

Connectivity

Nearest IXPMountain West Technologies - Casper
IXP distance34.6 mi
Fiber providers11
Fiber coverage65.2%

Site characteristics

Risk & environment

Water stress (WRI)Medium-High
Wetlands (NWI)
Critical habitat
Superfund nearby
Hazard sub-score90/100

Location context

Nearest datacenterMountain West Technologies - Casper
DC distance34.6 mi
County hazard (FEMA NRI)Very Low (10)
DC tax incentiveYes (no_income_tax)
Commercial electricity10.70¢/kWh
Industrial electricity7.94¢/kWh
Cooling degree days300
Heating degree days7,600
Land price / acre$825

Incentive detail: No state corporate or personal income tax; low property taxes.

Site location

◆ Loading map…
≥ 7560–7540–60≤ 40
This site + 8 nearby

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
46
Speed to power15%
40
Fiber connectivity12%
35
Energy cost10%
50
Water risk8%
48
Natural hazard8%
90
Buildability7%
60
Labor market4%
50
DC cluster4%
40
Land / acreage3%
55
Construction cost3%
50
Gas pipeline2%
10
Tax incentive2%
100
Climate / cooling2%
100

Nearby comparable sites

Other scored datacenter candidate sites in Natrona County, ranked by DC Readiness.

Sites near TAP209454
SiteTypeVoltageCapacityQueue waitScore
Chevron Casper Wind FarmBrownfield115 kV17 MW6.9 yrs69.2
UNKNOWN202379Substation-Adjacent230 kV300 MW6.9 yrs65.6
UNKNOWN201258Substation-Adjacent230 kV300 MW6.9 yrs65.5
TAP205652Substation-Adjacent230 kV300 MW6.9 yrs63.4
UNKNOWN209474Substation-Adjacent115 kV100 MW6.9 yrs61.7
UNKNOWN209472Substation-Adjacent115 kV100 MW6.9 yrs61.5
UNKNOWN209475Substation-Adjacent115 kV100 MW6.9 yrs61.4
UNKNOWN209477Substation-Adjacent115 kV100 MW6.9 yrs61.3

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for TAP209454, Natrona County. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.