Big Horn County, Wyoming · WECC

DC Readiness
54.0
Fair / 100

TAP208640 is a substation-adjacent datacenter candidate site in Big Horn County, Wyoming, interconnecting through WECC. It screens at 54.0/100 DC Readiness with a catalogued 50 MW of candidate capacity and a 6.9 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationTAP208640
Substation distance0.0 mi
Substation voltage69 kV
Available capacity50 MW

Speed to power

Interconnection outlookConstrained
≈ 6.9 yrs typical interconnection wait

Deep queue and long historical waits — plan for a multi-year interconnection timeline and engage the utility early.

ISO / RTO regionWECC
Queue depth34
Avg queue wait6.9 yrs

Connectivity

Nearest IXPACT Sheridan
IXP distance63.7 mi
Fiber providers3
Fiber coverage61.0%

Site characteristics

Risk & environment

Environmental constraintNone (0/100)
Flood zoneZone X
Water stress (WRI)Medium-High
Wetlands (NWI)—
Critical habitat—
Superfund nearby—
Hazard sub-score90/100

Location context

Nearest datacenterACT Sheridan
DC distance63.7 mi
County hazard (FEMA NRI)Very Low (10)
DC tax incentiveYes (no_income_tax)
Commercial electricity11.86¢/kWh
Industrial electricity7.63¢/kWh
Cooling degree days300
Heating degree days7,600
Land price / acre$2,313

Regulatory climate

Favorablestate posture · as of 2026-08

Low-cost power and land; DC-friendly posture.

DC tax incentiveYes

Incentive detail: No state corporate or personal income tax; low property taxes.

Site location

◆ Loading map…
≥ 7560–7540–60≤ 40
This site + 8 nearby

Get alerts

Track TAP208640

Get an email when its DC-readiness score, available capacity, or interconnection-queue status changes.

No spam. Just the alerts you asked for.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
46
Speed to power20%
55
Fiber connectivity12%
65
Energy cost10%
50
Water risk7%
48
Natural hazard6%
90
Buildability7%
60
Labor market4%
50
DC cluster4%
20
Land / acreage3%
55
Construction cost3%
50
Gas pipeline2%
10
Tax incentive1%
100
Climate / cooling1%
100

Nearby comparable sites

Other scored datacenter candidate sites in Big Horn County, ranked by DC Readiness.

Sites near TAP208640
SiteTypeVoltageCapacityQueue waitScore
EC Coal Big Horn CountyGreenfield——1.7 yrs61.0
EC Coal Big Horn CountyGreenfield——1.7 yrs60.4
GARLANDSubstation-Adjacent230 kV300 MW6.9 yrs60.3
UNKNOWN203003Substation-Adjacent230 kV300 MW6.9 yrs60.3
EC Coal Big Horn CountyGreenfield——1.7 yrs56.2
TAP208612Substation-Adjacent69 kV50 MW6.9 yrs55.0
UNKNOWN208635Substation-Adjacent69 kV50 MW6.9 yrs55.0
TAP208632Substation-Adjacent69 kV50 MW6.9 yrs55.0

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for TAP208640, Big Horn County. Pro and Enterprise plans unlock the full 147,272-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.