TAP204225 is a substation-adjacent datacenter candidate site in Albany County, Wyoming, interconnecting through WECC. It screens at 56.4/100 DC Readiness with a catalogued 100 MW of candidate capacity and a 6.9 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationTAP204225
Substation distance0.0 mi
Substation voltage115 kV
Available capacity100 MW

Speed to power

Interconnection outlookConstrained
≈ 6.9 yrs typical interconnection wait

Deep queue and long historical waits — plan for a multi-year interconnection timeline and engage the utility early.

ISO / RTO regionWECC
Queue depth34
Avg queue wait6.9 yrs

Connectivity

Nearest IXPACT Cheyenne
IXP distance35.9 mi
Fiber providers5
Fiber coverage63.3%

Site characteristics

Risk & environment

Environmental constraintNone (0/100)
Water stress (WRI)Medium-High
Wetlands (NWI)—
Critical habitat—
Superfund nearby—
Hazard sub-score90/100

Location context

Nearest datacenterCYS42 Datacenter
DC distance35.6 mi
County hazard (FEMA NRI)Very Low (10)
DC tax incentiveYes (no_income_tax)
Commercial electricity8.92¢/kWh
Industrial electricity8.58¢/kWh
Cooling degree days300
Heating degree days7,600
Land price / acre$1,040

Regulatory climate

Favorablestate posture · as of 2026-08

Low-cost power and land; DC-friendly posture.

DC tax incentiveYes

Incentive detail: No state corporate or personal income tax; low property taxes.

Site location

◆ Loading map…
≥ 7560–7540–60≤ 40
This site + 8 nearby

Get alerts

Track TAP204225

Get an email when its DC-readiness score, available capacity, or interconnection-queue status changes.

No spam. Just the alerts you asked for.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
56
Speed to power20%
40
Fiber connectivity12%
66
Energy cost10%
50
Water risk7%
48
Natural hazard6%
90
Buildability7%
60
Labor market4%
50
DC cluster4%
40
Land / acreage3%
55
Construction cost3%
50
Gas pipeline2%
10
Tax incentive1%
100
Climate / cooling1%
100

Nearby comparable sites

Other scored datacenter candidate sites in Albany County, ranked by DC Readiness.

Sites near TAP204225
SiteTypeVoltageCapacityQueue waitScore
OZ AlbanyGreenfield——1.7 yrs62.1
OZ AlbanyGreenfield——1.7 yrs61.3
OZ AlbanyGreenfield——1.7 yrs61.3
UNKNOWN202676Substation-Adjacent230 kV300 MW6.9 yrs60.9
UNKNOWN201269Substation-Adjacent230 kV300 MW6.9 yrs60.5
EC Coal Albany CountyGreenfield——1.7 yrs60.4
UNKNOWN204108Substation-Adjacent230 kV300 MW6.9 yrs60.2
UNKNOWN204224Substation-Adjacent245 kV300 MW6.9 yrs60.1

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

Every site and score for TAP204225, Albany County is free to browse. Pro adds Watchtower on 25 sites, alerts when new candidate sites, datacenters or interconnection-queue requests appear in your markets, score and capacity history, and CSV export. Enterprise adds team seats, weekly data files for all 147,272 sites, the REST API and an MCP server for AI tools.