Edgewood Ave and Douglas Ave Site - Parcel 2

Industrial

Racine County, Wisconsin · MISO

DC Readiness
54.3
Fair / 100

Edgewood Ave and Douglas Ave Site - Parcel 2 is an industrial datacenter candidate site in Racine County, Wisconsin, interconnecting through MISO. It screens at 54.3/100 DC Readiness and a 2.8 yrs average interconnection-queue wait.

Power & interconnection

UtilityWISCONSIN ELECTRIC POWER COinvestor ownedfavorable to large load · terms ≥ 100 MWVery Large Customer (VLC) tariff · 10 yr

Speed to power

Interconnection outlookFavorable
≈ 2.8 yrs typical interconnection wait

Shorter queues and healthier completion here — a faster path to energization than the national norm.

ISO / RTO regionMISO
Queue depth133
Avg queue wait2.8 yrs

Connectivity

Nearest IXPCyberLynk MKE1
IXP distance12.4 mi
Fiber providers6
Fiber coverage45.9%

Site characteristics

Site typeIndustrial

Risk & environment

Environmental constraintNone (0/100)
Water stress (WRI)Low
Wetlands (NWI)—
Critical habitat—
Superfund nearby—
Hazard sub-score78/100

Location context

Nearest datacenterMicrosoft Stargate (Mt Pleasant)
DC distance4.6 mi
County hazard (FEMA NRI)Relatively Low (22)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity13.75¢/kWh
Industrial electricity9.28¢/kWh
Cooling degree days600
Heating degree days7,200
Land price / acre$9,656

Regulatory climate

Moderatestate posture · as of 2026-08

No notable statewide DC restriction on record; confirm local zoning and utility tariffs.

DC tax incentiveNo / suspended

Incentive detail: Enterprise Zone tax credits; TIF available for DC construction in eligible areas.

Site location

◆ Loading map…
≥ 7560–7540–60≤ 40
This site + 8 nearby

Get alerts

Track Edgewood Ave and Douglas Ave Site - Parcel 2

Get an email when its DC-readiness score, available capacity, or interconnection-queue status changes.

No spam. Just the alerts you asked for.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
30
Speed to power20%
45
Fiber connectivity12%
78
Energy cost10%
50
Water risk7%
94
Natural hazard6%
78
Buildability7%
50
Labor market4%
50
DC cluster4%
80
Land / acreage3%
45
Construction cost3%
50
Gas pipeline2%
10
Tax incentive1%
100
Climate / cooling1%
95

Nearby comparable sites

Other scored datacenter candidate sites in Racine County, ranked by DC Readiness.

Sites near Edgewood Ave and Douglas Ave Site - Parcel 2
SiteTypeVoltageCapacityQueue waitScore
RACINESubstation-Adjacent345 kV600 MW2.8 yrs67.3
HAYESSubstation-Adjacent138 kV100 MW2.8 yrs61.2
Greenfield (RACINE - OAK CREEK STATION)Greenfield345 kV600 MW2.8 yrs60.7
ST. RITASubstation-Adjacent138 kV100 MW2.8 yrs60.6
OZ RacineGreenfield——1.4 yrs60.1
Mine SiteFormer Mine——2.8 yrs55.1
Greenfield (RACINE - ST. RITA)Greenfield138 kV100 MW2.8 yrs54.7
Racine MetalsIndustrial——2.8 yrs54.3

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.