Sky Park Solar

Brownfield

Eau Claire, Wisconsin · MISO

DC Readiness
64.2
Good / 100

Sky Park Solar is a brownfield datacenter candidate site in Eau Claire, Wisconsin, interconnecting through MISO. It screens at 64.2/100 DC Readiness with a catalogued 1 MW of candidate capacity.

Power & interconnection

Substation distance1.8 mi
Available capacity1 MW
LMP zoneMISO_MISO_CENTRAL
Wholesale LMP$27.30/MWh
Utility commercial rate0.12¢/kWh

Speed to power

ISO / RTO regionMISO
Queue depth41

Connectivity

Nearest IXP901 Commerce Dr
IXP distance66.4 mi
Fiber providers10
Nearest cloud providerAzure
Nearest cloud regioncentralus
Cloud region distance247.7 mi

Site characteristics

Site typeBrownfield
Acreage26 ac
Land owner typeprivate
Buildability75.0/100
Former uselandfill
Existing capacity1 MW
Cleanup statuscleanup_complete

Risk & environment

Flood zoneZone X
Water stress (WRI)0.30
Wetlands (NWI)Clear
Critical habitatClear
Superfund nearbyPresent
Superfund siteBANBURY PLACE
Hazard sub-score68/100
Construction cost index90.8 (avg 100)

Location context

Nearest datacenterWest Wisconsin Telcom DC
DC distance21.2 mi
Nearest rail0.3 mi
Nearest gas pipeline2.1 mi
County hazard (FEMA NRI)Relatively Low (22)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity11.78¢/kWh
Industrial electricity8.61¢/kWh
Cooling degree days600
Heating degree days7,200
Land price / acre$6,093

Incentive detail: Enterprise Zone tax credits; TIF available for DC construction in eligible areas.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
39
Speed to power15%
40
Fiber connectivity12%
75
Energy cost10%
94
Water risk8%
94
Natural hazard8%
68
Buildability7%
75
Labor market4%
50
DC cluster4%
60
Land / acreage3%
47
Construction cost3%
74
Gas pipeline2%
93
Tax incentive2%
100
Climate / cooling2%
95

Nearby comparable sites

Other scored datacenter candidate sites in Eau Claire, ranked by DC Readiness.

Sites near Sky Park Solar
SiteTypeVoltageCapacityQueue waitScore
SEVEN MILESubstation-Adjacent161 kV100 MW1.4 yrs71.0
UNKNOWN161952Substation-Adjacent161 kV100 MW1.4 yrs70.8
TAP163522Substation-Adjacent161 kV100 MW1.4 yrs70.2
UNKNOWN143576Substation-Adjacent161 kV100 MW1.4 yrs70.2
UNKNOWN163509Substation-Adjacent161 kV100 MW1.4 yrs69.3
UNKNOWN131390Substation-Adjacent161 kV100 MW1.4 yrs67.1
Greenfield (UNKNOWN129869 - ARPIN)Greenfield345 kV600 MW1.4 yrs65.6
Greenfield (SEVEN MILE - TREMVAL)Greenfield161 kV100 MW1.4 yrs64.4

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen