Eau Claire County, Wisconsin · MISO

DC Readiness
58.8
Good / 100

SEVEN MILE is a substation-adjacent datacenter candidate site in Eau Claire County, Wisconsin, interconnecting through MISO. It screens at 58.8/100 DC Readiness with a catalogued 100 MW of candidate capacity and a 2.8 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationSEVEN MILE
Substation distance0.0 mi
Substation voltage161 kV
Available capacity100 MW
UtilityEAU CLAIRE ELECTRIC COOPnot available

Speed to power

Interconnection outlookFavorable
≈ 2.8 yrs typical interconnection wait

Shorter queues and healthier completion here — a faster path to energization than the national norm.

ISO / RTO regionMISO
Queue depth133
Avg queue wait2.8 yrs

Connectivity

Nearest IXP901 Commerce Dr
IXP distance60.3 mi
Fiber providers10
Fiber coverage60.0%

Site characteristics

Risk & environment

Environmental constraintNone (0/100)
Water stress (WRI)Low
Wetlands (NWI)
Critical habitat
Superfund nearby
Hazard sub-score78/100

Location context

Nearest datacenterWest Wisconsin Telcom DC
DC distance27.3 mi
County hazard (FEMA NRI)Relatively Low (22)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity11.78¢/kWh
Industrial electricity8.61¢/kWh
Cooling degree days600
Heating degree days7,200
Land price / acre$6,093

Regulatory climate

Moderatestate posture · as of 2026-08

No notable statewide DC restriction on record; confirm local zoning and utility tariffs.

DC tax incentiveNo / suspended

Incentive detail: Enterprise Zone tax credits; TIF available for DC construction in eligible areas.

Site location

◆ Loading map…
≥ 7560–7540–60≤ 40
This site + 8 nearby

Get alerts

Track SEVEN MILE

Get an email when its DC-readiness score, available capacity, or interconnection-queue status changes.

No spam. Just the alerts you asked for.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
60
Speed to power20%
45
Fiber connectivity12%
67
Energy cost10%
50
Water risk7%
94
Natural hazard6%
78
Buildability7%
60
Labor market4%
50
DC cluster4%
60
Land / acreage3%
45
Construction cost3%
50
Gas pipeline2%
10
Tax incentive1%
100
Climate / cooling1%
95

Nearby comparable sites

Other scored datacenter candidate sites in Eau Claire County, ranked by DC Readiness.

Sites near SEVEN MILE
SiteTypeVoltageCapacityQueue waitScore
UNKNOWN129869Substation-Adjacent345 kV600 MW2.8 yrs64.3
UNKNOWN131980Substation-Adjacent161 kV100 MW2.8 yrs59.9
EC Near Seven Mile Creek LFGGreenfield1.4 yrs59.3
OZ Eau ClaireGreenfield1.4 yrs59.0
TAP163522Substation-Adjacent161 kV100 MW2.8 yrs58.9
UNKNOWN161952Substation-Adjacent161 kV100 MW2.8 yrs58.8
UNKNOWN143576Substation-Adjacent161 kV100 MW2.8 yrs58.8
UNKNOWN143571Substation-Adjacent161 kV100 MW2.8 yrs58.7

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.