EC Coal Pendleton County

Greenfield

Pendleton County, West Virginia · PJM

DC Readiness
54.3
Fair / 100

EC Coal Pendleton County is a greenfield datacenter candidate site in Pendleton County, West Virginia, interconnecting through PJM. It screens at 54.3/100 DC Readiness and a 3.0 yrs average interconnection-queue wait.

Power & interconnection

LMP zonePJM_APS
Wholesale LMP$43.66/MWh
Utility commercial rate0.11¢/kWh

Speed to power

ISO / RTO regionPJM
Queue depth118
Avg queue wait3.0 yrs
Recent queue wait4.0 yrs
Completion rate23%
Withdrawal rate77%

Connectivity

Nearest IXPCitynet Bridgeport
IXP distance56.2 mi
Fiber providers4
Fiber coverage53.9%
Nearest cloud providerAzure
Nearest cloud regioneastus
Cloud region distance97.6 mi

Site characteristics

Site typeGreenfield
Parcel ownerHalterman Michael Shawn & Halterman Dawn Kelly
Land owner typeprivate
Buildability45.0/100
Land cover (NLCD)Deciduous Forest
Former usecoal adjacent

Risk & environment

Flood zoneZone X
Water stress (WRI)0.40
Wetlands (NWI)Clear
Critical habitatPresent
Superfund nearbyClear
Hazard sub-score58/100
Construction cost index43.0 (avg 100)

Location context

Nearest datacenterDBT Data - Harrisonburg Center
DC distance38.6 mi
Nearest rail15.6 mi
Nearest gas pipeline7.1 mi
Nearest fiber route62.2 mi
County hazard (FEMA NRI)Relatively Low (22)
DC tax incentiveNo
Commercial electricity10.92¢/kWh
Industrial electricity7.71¢/kWh
Cooling degree days800
Heating degree days5,000
Land price / acre$3,163

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
30
Speed to power15%
46
Fiber connectivity12%
54
Energy cost10%
81
Water risk8%
93
Natural hazard8%
58
Buildability7%
45
Labor market4%
50
DC cluster4%
45
Land / acreage3%
50
Construction cost3%
100
Gas pipeline2%
77
Tax incentive2%
0
Climate / cooling2%
85

Nearby comparable sites

Other scored datacenter candidate sites in Pendleton County, ranked by DC Readiness.

Sites near EC Coal Pendleton County
SiteTypeVoltageCapacityQueue waitScore
VALLEYSubstation-Adjacent500 kV1,000 MW3.0 yrs69.9
Greenfield (MOUNT STORM - VALLEY)Greenfield500 kV1,000 MW3.0 yrs65.0
Greenfield (MOUNT STORM - VALLEY)Greenfield500 kV1,000 MW3.0 yrs60.9
EC FFE Pendleton CountyGreenfield3.0 yrs50.9

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for EC Coal Pendleton County, Pendleton County. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.