EC Coal Jackson County is a greenfield datacenter candidate site in Jackson County, West Virginia, interconnecting through PJM. It screens at 55.9/100 DC Readiness and a 3.0 yrs average interconnection-queue wait.

Power & interconnection

LMP zonePJM_APS
Wholesale LMP$43.66/MWh
Utility commercial rate0.12¢/kWh

Speed to power

ISO / RTO regionPJM
Queue depth118
Avg queue wait3.0 yrs
Recent queue wait4.0 yrs
Completion rate23%
Withdrawal rate77%

Connectivity

Nearest IXPSecureNet DC1
IXP distance41.7 mi
Fiber providers2
Fiber coverage50.6%
Nearest cloud providerAWS
Nearest cloud regionus-east-2
Cloud region distance99.3 mi

Site characteristics

Site typeGreenfield
Parcel ownerHupp O C Clifford Hupp Clyde Hupp Clair Hupp Robert Hupp &
Land owner typeprivate
Buildability45.0/100
Land cover (NLCD)Deciduous Forest
Former usecoal adjacent

Risk & environment

Flood zoneZone X
Water stress (WRI)0.40
Wetlands (NWI)Clear
Critical habitatClear
Superfund nearbyClear
Hazard sub-score78/100
Construction cost index133.1 (avg 100)

Location context

Nearest datacenterSecureNet DC1
DC distance41.7 mi
Nearest rail5.9 mi
Nearest gas pipeline3.5 mi
Nearest fiber route127.0 mi
County hazard (FEMA NRI)Relatively Low (22)
DC tax incentiveNo
Commercial electricity11.84¢/kWh
Industrial electricity8.39¢/kWh
Cooling degree days800
Heating degree days5,000
Land price / acre$2,620

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
30
Speed to power15%
46
Fiber connectivity12%
58
Energy cost10%
93
Water risk8%
91
Natural hazard8%
78
Buildability7%
45
Labor market4%
50
DC cluster4%
45
Land / acreage3%
51
Construction cost3%
39
Gas pipeline2%
89
Tax incentive2%
0
Climate / cooling2%
85

Nearby comparable sites

Other scored datacenter candidate sites in Jackson County, ranked by DC Readiness.

Sites near EC Coal Jackson County
SiteTypeVoltageCapacityQueue waitScore
Greenfield (JOHN AMOS - MOUNTAINTEER)Greenfield765 kV1,000 MW3.2 yrs67.6
Greenfield (AMOS - SPORN)Greenfield345 kV600 MW3.2 yrs65.3
Greenfield (AMOS - SPORN)Greenfield345 kV600 MW3.2 yrs64.9
Greenfield (BELMONT - MOUNTAINTEER)Greenfield765 kV1,000 MW3.2 yrs64.4
Greenfield (BELMONT - MOUNTAINTEER)Greenfield765 kV1,000 MW3.2 yrs64.1
UNKNOWN137229Substation-Adjacent138 kV100 MW3.2 yrs63.9
Greenfield (BELMONT - MOUNTAINTEER)Greenfield765 kV1,000 MW3.2 yrs62.5
TAP137227Substation-Adjacent138 kV100 MW3.2 yrs61.8

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.