Kittitas County, Washington · WECC

DC Readiness
53.2
Fair / 100

TERRY is a substation-adjacent datacenter candidate site in Kittitas County, Washington, interconnecting through WECC. It screens at 53.2/100 DC Readiness with a catalogued 100 MW of candidate capacity and a 6.9 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationTERRY
Substation distance0.0 mi
Substation voltage115 kV
Available capacity100 MW

Speed to power

ISO / RTO regionWECC
Queue depth34
Avg queue wait6.9 yrs

Connectivity

Nearest IXPH5 Data Centers Quincy 2/3
IXP distance26.7 mi
Fiber providers7
Fiber coverage24.8%

Site characteristics

Risk & environment

Water stress (WRI)Low-Medium
Wetlands (NWI)
Critical habitat
Superfund nearby
Hazard sub-score72/100

Location context

Nearest datacenterMicrosoft EAT04
DC distance5.0 mi
County hazard (FEMA NRI)Relatively Moderate (28)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity7.38¢/kWh
Industrial electricity6.15¢/kWh
Cooling degree days300
Heating degree days5,000
Land price / acre$4,287

Incentive detail: Sales tax exemption on DC equipment and construction for eligible facilities; no state income tax.

Site location

◆ Loading map…
≥ 7560–7540–60≤ 40
This site + 8 nearby

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
56
Speed to power15%
42
Fiber connectivity12%
27
Energy cost10%
50
Water risk8%
64
Natural hazard8%
72
Buildability7%
60
Labor market4%
50
DC cluster4%
80
Land / acreage3%
48
Construction cost3%
50
Gas pipeline2%
10
Tax incentive2%
100
Climate / cooling2%
100

Nearby comparable sites

Other scored datacenter candidate sites in Kittitas County, ranked by DC Readiness.

Sites near TERRY
SiteTypeVoltageCapacityQueue waitScore
UNKNOWN201272Substation-Adjacent230 kV300 MW6.9 yrs60.7
SCHULTZSubstation-Adjacent500 kV1,000 MW6.9 yrs60.2
OZ KittitasGreenfield1.7 yrs59.5
WILD HORSESubstation-Adjacent230 kV300 MW6.9 yrs57.3
UNKNOWN203019Substation-Adjacent230 kV300 MW6.9 yrs57.0
WIND RIDGESubstation-Adjacent230 kV300 MW6.9 yrs56.9
TAP209256Substation-Adjacent115 kV100 MW6.9 yrs56.6
KEOKUKSubstation-Adjacent115 kV100 MW6.9 yrs56.0

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.