5901-5921 Thurston Ave - Airport Industrial Center II is a shovel-ready datacenter candidate site in Virginia Beach County, Virginia, interconnecting through PJM. It screens at 56.5/100 DC Readiness and a 3.8 yrs average interconnection-queue wait.

Power & interconnection

UtilityVIRGINIA ELECTRIC & POWER COinvestor ownedmoderate to large load · terms ≥ 25 MWSchedule GS-5 (large general service, ≥25 MW) · 85% min take · 14 yr

Speed to power

Interconnection outlookConstrained
≈ 3.8 yrs typical interconnection wait

Deep queue and long historical waits — plan for a multi-year interconnection timeline and engage the utility early.

ISO / RTO regionPJM
Queue depth878
Avg queue wait3.8 yrs

Connectivity

Nearest IXPLumen Norfolk
IXP distance2.1 mi
Fiber providers7
Fiber coverage80.8%

Site characteristics

Site typeShovel-Ready

Risk & environment

Environmental constraintNone (0/100)
Water stress (WRI)Low
Wetlands (NWI)—
Critical habitat—
Superfund nearby—
Hazard sub-score70/100

Location context

Nearest datacenterLumen Norfolk
DC distance2.1 mi
County hazard (FEMA NRI)Relatively Moderate (30)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity4.81¢/kWh
Industrial electricity4.19¢/kWh
Cooling degree days1,300
Heating degree days4,000
Land price / acre$8,304

Regulatory climate

Moderatestate posture · as of 2026-08

Largest US DC market; incentive preserved but a new $0.011/kWh DC electricity tax starts Jul 2026.

DC tax incentiveYes
Large-load threshold≥ 25 MW

Dominion GS-5 large-load rate (≥25 MW, ~$1.5M/MW collateral, 14-yr term) effective 2027.

Incentive detail: Sales tax exemption on DC equipment for $150M+ investments (2025: $100M+); MEGA site program.

Site location

◆ Loading map…
≥ 7560–7540–60≤ 40
This site + 8 nearby

Get alerts

Track 5901-5921 Thurston Ave - Airport Industrial Center II

Get an email when its DC-readiness score, available capacity, or interconnection-queue status changes.

No spam. Just the alerts you asked for.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
30
Speed to power20%
38
Fiber connectivity12%
96
Energy cost10%
50
Water risk7%
88
Natural hazard6%
70
Buildability7%
50
Labor market4%
50
DC cluster4%
100
Land / acreage3%
46
Construction cost3%
50
Gas pipeline2%
10
Tax incentive1%
100
Climate / cooling1%
60

Nearby comparable sites

Other scored datacenter candidate sites in Virginia Beach County, ranked by DC Readiness.

Sites near 5901-5921 Thurston Ave - Airport Industrial Center II
SiteTypeVoltageCapacityQueue waitScore
LONDON BRIDGESubstation-Adjacent230 kV300 MW3.8 yrs66.1
PENDLETONSubstation-Adjacent230 kV300 MW3.8 yrs66.0
THALIASubstation-Adjacent230 kV300 MW3.8 yrs65.4
LANDSTOWNSubstation-Adjacent230 kV300 MW3.8 yrs65.2
LYNNHAVENSubstation-Adjacent230 kV300 MW3.8 yrs65.2
STUMPY LAKESubstation-Adjacent230 kV300 MW3.8 yrs65.2
UNKNOWN115502Substation-Adjacent230 kV300 MW3.8 yrs65.2
TAP147081Substation-Adjacent230 kV300 MW3.8 yrs65.2

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

Every site and score for 5901-5921 Thurston Ave - Airport Industrial Center II, Virginia Beach County is free to browse. Pro adds Watchtower on 25 sites, alerts when new candidate sites, datacenters or interconnection-queue requests appear in your markets, score and capacity history, and CSV export. Enterprise adds team seats, weekly data files for all 147,272 sites, the REST API and an MCP server for AI tools.