EC FFE Martinsville city

Greenfield

Martinsville, Virginia · PJM

DC Readiness
60.7
Good / 100

EC FFE Martinsville city is a greenfield datacenter candidate site in Martinsville, Virginia, interconnecting through PJM. It screens at 60.7/100 DC Readiness and a 3.1 yrs average interconnection-queue wait.

Power & interconnection

LMP zonePJM_DOM
Wholesale LMP$43.92/MWh

Speed to power

ISO / RTO regionPJM
Queue depth864
Avg queue wait3.1 yrs
Recent queue wait3.6 yrs
Completion rate20%
Withdrawal rate80%

Connectivity

Nearest IXPCyrusOne NC-1
IXP distance75.2 mi
Fiber providers2
Fiber coverage94.6%
Nearest cloud providerAzure
Nearest cloud regioneastus
Cloud region distance47.7 mi

Site characteristics

Site typeGreenfield
Parcel ownerAPPALACHIAN POWER CO
Land owner typeprivate
Buildability92.0/100
Land cover (NLCD)Developed, Low Intensity
Former usefossil fuel employment

Risk & environment

Flood zoneZone X
Water stress (WRI)0.60
Wetlands (NWI)Clear
Critical habitatClear
Superfund nearbyPresent
Superfund siteVDOT BRIDGE STRUCTURE 10059
Hazard sub-score60/100
Construction cost index97.5 (avg 100)

Location context

Nearest datacenterLumos Networks
DC distance64.4 mi
Nearest rail0.8 mi
Nearest gas pipeline4.9 mi
Nearest fiber route14.3 mi
County hazard (FEMA NRI)Relatively Moderate (30)
DC tax incentiveYes (sales_tax_exemption)
Cooling degree days1,300
Heating degree days4,000
Land price / acre$5,900

Incentive detail: Sales tax exemption on DC equipment for $150M+ investments (2025: $100M+); MEGA site program.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
30
Speed to power15%
44
Fiber connectivity12%
74
Energy cost10%
88
Water risk8%
89
Natural hazard8%
60
Buildability7%
92
Labor market4%
50
DC cluster4%
30
Land / acreage3%
61
Construction cost3%
69
Gas pipeline2%
84
Tax incentive2%
100
Climate / cooling2%
60

Nearby comparable sites

Other scored datacenter candidate sites in Martinsville, ranked by DC Readiness.

Sites near EC FFE Martinsville city
SiteTypeVoltageCapacityQueue waitScore
Greenfield (AXTON - JACKSONS FERRY)Greenfield765 kV1,000 MW3.1 yrs68.3
UNKNOWN114625Substation-Adjacent138 kV100 MW3.1 yrs65.4
FIELDALESubstation-Adjacent138 kV100 MW3.1 yrs65.4
RIDGEWAYSubstation-Adjacent138 kV100 MW3.1 yrs64.4
Greenfield (AXTON - JACKSONS FERRY)Greenfield765 kV1,000 MW3.1 yrs63.1
THORNTONSubstation-Adjacent138 kV100 MW3.1 yrs62.2
Greenfield (AXTON - JACKSONS FERRY)Greenfield765 kV1,000 MW3.1 yrs61.9
OZ MartinsvilleGreenfield3.1 yrs60.7

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for EC FFE Martinsville city, Martinsville. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.