UNKNOWN114182

Substation-Adjacent

Lynchburg city, Virginia · PJM

DC Readiness
57.7
Good / 100

UNKNOWN114182 is a substation-adjacent datacenter candidate site in Lynchburg city, Virginia, interconnecting through PJM. It screens at 57.7/100 DC Readiness with a catalogued 100 MW of candidate capacity and a 3.8 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationUNKNOWN114182
Substation distance0.0 mi
Substation voltage138 kV
Available capacity100 MW

Speed to power

Interconnection outlookConstrained
≈ 3.8 yrs typical interconnection wait

Deep queue and long historical waits — plan for a multi-year interconnection timeline and engage the utility early.

ISO / RTO regionPJM
Queue depth878
Avg queue wait3.8 yrs

Connectivity

Nearest IXPEquinix CU1/CU2/CU3/CU4 - Culpeper
IXP distance104.6 mi
Fiber providers5
Fiber coverage78.4%

Site characteristics

Risk & environment

Environmental constraintNone (0/100)
Water stress (WRI)Low
Wetlands (NWI)
Critical habitat
Superfund nearby
Hazard sub-score70/100

Location context

Nearest datacenterLumos Networks
DC distance12.2 mi
County hazard (FEMA NRI)Relatively Moderate (30)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity7.67¢/kWh
Industrial electricity5.33¢/kWh
Cooling degree days1,300
Heating degree days4,000
Land price / acre$5,900

Regulatory climate

Moderatestate posture · as of 2026-08

Largest US DC market; incentive preserved but a new $0.011/kWh DC electricity tax starts Jul 2026.

DC tax incentiveYes
Large-load threshold≥ 25 MW

Dominion GS-5 large-load rate (≥25 MW, ~$1.5M/MW collateral, 14-yr term) effective 2027.

Incentive detail: Sales tax exemption on DC equipment for $150M+ investments (2025: $100M+); MEGA site program.

Site location

◆ Loading map…
≥ 7560–7540–60≤ 40
This site + 8 nearby

Get alerts

Track UNKNOWN114182

Get an email when its DC-readiness score, available capacity, or interconnection-queue status changes.

No spam. Just the alerts you asked for.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
58
Speed to power20%
41
Fiber connectivity12%
70
Energy cost10%
50
Water risk7%
88
Natural hazard6%
70
Buildability7%
60
Labor market4%
50
DC cluster4%
80
Land / acreage3%
46
Construction cost3%
50
Gas pipeline2%
10
Tax incentive1%
100
Climate / cooling1%
60

Nearby comparable sites

Other scored datacenter candidate sites in Lynchburg city, ranked by DC Readiness.

Sites near UNKNOWN114182
SiteTypeVoltageCapacityQueue waitScore
JOSHUA FALLSSubstation-Adjacent765 kV1,000 MW3.8 yrs66.3
OZ LynchburgGreenfield3.1 yrs62.5
Greenfield (CLOVERDALE 765KV - JOSHUA FALL)Greenfield765 kV1,000 MW3.8 yrs59.9
MONELSubstation-Adjacent138 kV100 MW3.8 yrs58.7
PEAKSVIEWSubstation-Adjacent138 kV100 MW3.8 yrs58.7
REUSENSSubstation-Adjacent138 kV100 MW3.8 yrs57.9
IVY HILLSubstation-Adjacent138 kV100 MW3.8 yrs57.9
JOSHUA FALLSSubstation-Adjacent138 kV100 MW3.8 yrs57.9

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for UNKNOWN114182, Lynchburg city. Pro and Enterprise plans unlock the full 147,272-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.