Skip to content
Gridcensus

Mine Site

Former Mine

Rutland County, Vermont · ISO-NE

DC Readiness
53.6
Fair / 100

Mine Site is a former mine datacenter candidate site in Rutland County, Vermont, interconnecting through ISO-NE. It screens at 53.6/100 DC Readiness and a 3.9 yrs average interconnection-queue wait.

Power & interconnection

UtilityGREEN MOUNTAIN POWER CORPinvestor ownedmoderate to large load · terms ≥ 25 MW

Speed to power

Interconnection outlookModerate
≈ 3.9 yrs typical interconnection wait

Middle-of-the-pack interconnection conditions for this grid.

ISO / RTO regionISO-NE
Queue depth5
Avg queue wait3.9 yrs

Connectivity

Nearest IXPVELCO Rutland
IXP distance12.8 mi
Fiber providers7
Fiber coverage89.4%

Site characteristics

Site typeFormer Mine
Former useMining: SandAndGravel; Status: Abandoned
Cleanup statusAbandoned

Risk & environment

Environmental constraintNone (0/100)
Water stress (WRI)Low
Wetlands (NWI)—
Critical habitat—
Superfund nearby—
Hazard sub-score85/100

Location context

Nearest datacenterVELCO Rutland
DC distance12.8 mi
County hazard (FEMA NRI)Relatively Low (15)
DC tax incentiveNo
Commercial electricity19.25¢/kWh
Industrial electricity10.84¢/kWh
Cooling degree days400
Heating degree days7,400
Land price / acre$3,393

Regulatory climate

Moderatestate posture · as of 2026-08

No notable statewide DC restriction on record; confirm local zoning and utility tariffs.

DC tax incentiveNo / suspended

Site location

◆ Loading map…
≥ 7560–7540–60≤ 40
This site + 8 nearby

Get alerts

Track Mine Site

Get an email when its DC-readiness score, available capacity, or interconnection-queue status changes.

No spam. Just the alerts you asked for.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
30
Speed to power20%
36
Fiber connectivity12%
90
Energy cost10%
50
Water risk7%
94
Natural hazard6%
85
Buildability7%
50
Labor market4%
50
DC cluster4%
80
Land / acreage3%
49
Construction cost3%
50
Gas pipeline2%
10
Tax incentive1%
0
Climate / cooling1%
100

Nearby comparable sites

Other scored datacenter candidate sites in Rutland County, ranked by DC Readiness.

Sites near Mine Site
SiteTypeVoltageCapacityQueue waitScore
WEST RUTLANDSubstation-Adjacent345 kV600 MW3.9 yrs66.6
Rutland Landfill (Stafford Hill)Brownfield46 kV2 MW3.9 yrs63.4
OZ RutlandGreenfield——3.5 yrs62.5
NORTH RUTLANDSubstation-Adjacent115 kV100 MW3.9 yrs61.3
UNKNOWN133349Substation-Adjacent115 kV100 MW3.9 yrs60.2
TAP136049Substation-Adjacent115 kV100 MW3.9 yrs60.1
BLISSVILLESubstation-Adjacent115 kV100 MW3.9 yrs59.4
WHITEHALLSubstation-Adjacent115 kV100 MW4.9 yrs58.1

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for Mine Site, Rutland County. Pro and Enterprise plans unlock the full 147,272-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.