Addison County, Vermont · ISO-NE

DC Readiness
56.8
Good / 100

MIDDLEBURY is a substation-adjacent datacenter candidate site in Addison County, Vermont, interconnecting through ISO-NE. It screens at 56.8/100 DC Readiness with a catalogued 100 MW of candidate capacity and a 3.9 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationMIDDLEBURY
Substation distance0.0 mi
Substation voltage115 kV
Available capacity100 MW
UtilityGREEN MOUNTAIN POWER CORPinvestor ownedmoderate to large load · terms ≥ 25 MW

Speed to power

Interconnection outlookModerate
≈ 3.9 yrs typical interconnection wait

Middle-of-the-pack interconnection conditions for this grid.

ISO / RTO regionISO-NE
Queue depth5
Avg queue wait3.9 yrs

Connectivity

Nearest IXPVELCO Rutland
IXP distance25.5 mi
Fiber providers7
Fiber coverage68.3%

Site characteristics

Risk & environment

Environmental constraintNone (0/100)
Water stress (WRI)Low
Wetlands (NWI)—
Critical habitat—
Superfund nearby—
Hazard sub-score85/100

Location context

Nearest datacenterVELCO Rutland
DC distance25.5 mi
County hazard (FEMA NRI)Relatively Low (15)
DC tax incentiveNo
Commercial electricity19.20¢/kWh
Industrial electricity10.97¢/kWh
Cooling degree days400
Heating degree days7,400
Land price / acre$3,832

Regulatory climate

Moderatestate posture · as of 2026-08

No notable statewide DC restriction on record; confirm local zoning and utility tariffs.

DC tax incentiveNo / suspended

Site location

◆ Loading map…
≥ 7560–7540–60≤ 40
This site + 8 nearby

Get alerts

Track MIDDLEBURY

Get an email when its DC-readiness score, available capacity, or interconnection-queue status changes.

No spam. Just the alerts you asked for.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
56
Speed to power20%
36
Fiber connectivity12%
74
Energy cost10%
50
Water risk7%
94
Natural hazard6%
85
Buildability7%
60
Labor market4%
50
DC cluster4%
60
Land / acreage3%
49
Construction cost3%
50
Gas pipeline2%
10
Tax incentive1%
0
Climate / cooling1%
100

Nearby comparable sites

Other scored datacenter candidate sites in Addison County, ranked by DC Readiness.

Sites near MIDDLEBURY
SiteTypeVoltageCapacityQueue waitScore
NEW HAVENSubstation-Adjacent345 kV600 MW3.9 yrs63.3
EC Near Vergennes 9Greenfield——3.5 yrs58.1
EC Near Vergennes 9Greenfield——3.5 yrs57.6
EC Near Vergennes 9Greenfield——3.5 yrs57.5
UNKNOWN139869Substation-Adjacent115 kV100 MW3.9 yrs57.4
UNKNOWN127985Substation-Adjacent115 kV100 MW4.9 yrs57.0
EC Near Vergennes 9Greenfield——3.5 yrs57.0
UNKNOWN127980Substation-Adjacent115 kV100 MW4.9 yrs56.9

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for MIDDLEBURY, Addison County. Pro and Enterprise plans unlock the full 147,272-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.