DC Readiness
61.3
Good / 100

TAP206368 is a substation-adjacent datacenter candidate site in Davis County, Utah, interconnecting through WECC. It screens at 61.3/100 DC Readiness with a catalogued 300 MW of candidate capacity and a 6.9 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationTAP206368
Substation distance0.0 mi
Substation voltage230 kV
Available capacity300 MW

Speed to power

ISO / RTO regionWECC
Queue depth34
Avg queue wait6.9 yrs

Connectivity

Nearest IXPLowest Host/Empire Technology
IXP distance12.9 mi
Fiber providers13
Fiber coverage92.7%

Site characteristics

Risk & environment

Water stress (WRI)High
Wetlands (NWI)
Critical habitat
Superfund nearby
Hazard sub-score85/100

Location context

Nearest datacenterLowest Host/Empire Technology
DC distance12.9 mi
County hazard (FEMA NRI)Relatively Low (15)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity9.95¢/kWh
Industrial electricity7.91¢/kWh
Cooling degree days1,000
Heating degree days5,500
Land price / acre$14,480

Incentive detail: Enterprise Zone tax credits; Economic Development Tax Increment Financing (EDTIF).

Site location

◆ Loading map…
≥ 7560–7540–60≤ 40
This site + 8 nearby

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
78
Speed to power15%
44
Fiber connectivity12%
77
Energy cost10%
50
Water risk8%
24
Natural hazard8%
85
Buildability7%
60
Labor market4%
50
DC cluster4%
80
Land / acreage3%
51
Construction cost3%
50
Gas pipeline2%
10
Tax incentive2%
100
Climate / cooling2%
75

Nearby comparable sites

Other scored datacenter candidate sites in Davis County, ranked by DC Readiness.

Sites near TAP206368
SiteTypeVoltageCapacityQueue waitScore
EC Near Bountiful CityGreenfield1.7 yrs63.1
EC Near Bountiful CityGreenfield1.7 yrs63.1
EC Near Bountiful CityGreenfield1.7 yrs62.8
OZ DavisGreenfield1.7 yrs62.1
EC Near Bountiful CityGreenfield1.7 yrs61.8
UNKNOWN206367Substation-Adjacent230 kV300 MW6.9 yrs60.9
EC Near Bountiful CityGreenfield1.7 yrs60.8
SYRACUSESubstation-Adjacent345 kV600 MW6.9 yrs60.7

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for TAP206368, Davis County. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.